Paragraph 20 Access to work – provision of informationI1

England, Wales and Scotland

(1)

The undertaker on being given reasonable notice must—

(a)

at all reasonable times allow reasonable facilities to the engineer for access to a specified work during its construction and, to the extent that it would affect the waterway or any function of the Trust, maintenance; and

(b)

supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing and maintaining it.

(2)

The Trust on being given reasonable notice must supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them and the undertaker must reimburse the Trust’s reasonable costs in relation to the supply of such information.

Annotations

Commencement

I1

Sch. 15 para. 20 in force at 5.4.2024, see art. 1