Paragraph 2 Time limitsI1
England, Wales and Scotland
The authorised development must be commenced within 5 years of the date of this Order.
F1If any proceedings are begun to challenge the validity of this Order, the period specified in paragraph (1) is extended by —
a period equivalent to the period beginning with the day the application is made and ending on the day it is withdrawn or finally determined, or
if shorter, one year.
An application is not finally determined for the purposes of F2paragraph (2)(a) if an appeal in respect of the application—
could be brought (ignoring any possibility of an appeal out of time with permission), or
has been made and not withdrawn or finally determined.
Annotations
Textual amendments
- F1
Words in Sch. 3 para. 2(2) substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
- F2
Words in Sch. 3 para. 2(3) substituted (12.6.2024) by The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 (S.I. 2024/811), art. 1, Sch. 1
Commencement
- I1
Sch. 3 para. 2 in force at 5.4.2024, see art. 1