Article 4 Development consent etc. granted by this OrderI1
England, Wales and Scotland
(1)
Subject to the provisions of this Order and to the Requirements, NZT Power is granted development consent for Project A to be carried out within the Order limits.
(2)
Subject to the provisions of this Order and to the Requirements, NZNS Storage is granted development consent for Project B to be carried out within the Order limits.
(3)
Each numbered work must be carried out within the Order limits and situated within the corresponding numbered area shown on the works plans.
Annotations
Commencement
- I1
Art. 4 in force at 11.3.2024, see art. 1