The Net Zero Teesside Order 2024

S.I. 2024/174 · Made 16 February 2024 · Extends to England, Wales and Scotland

Up to date with all changes known to legislation.gov.uk, revised to 29 July 2026.

Infrastructure Planning

Made

16th February 2024

Coming into force

11th March 2024

An application has been made to the Secretary of State under section 37 (applications for orders granting development consent) of the Planning Act 2008f1 (the “2008 Act”) in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009f2 for an Order granting development consent.

The application was examined by a Panel as Examining authority appointed by the Secretary of State pursuant to sections 61f3 and 65f4 of Part 6 of the 2008 Act and carried out in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f5. The Examining authority having considered the application with the documents that accompanied the application, and the representations made and not withdrawn, has, in accordance with section 74(2)f6 of the 2008 Act, submitted a report and recommendation to the Secretary of State.

The Secretary of State having considered the representations made and not withdrawn, the report and recommendation of the Examining authority and having taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017f7 and having had regard to the documents and matters referred to in section 104(2)f8 (decisions in cases where national policy statement has effect) of the 2008 Act has determined to make an Order granting development consent for the development comprised in the application on terms that, in the opinion of the Secretary of State, are not materially different from those comprised in the application.

The Secretary of State is satisfied that open space comprised within the Order land, when burdened with the new rights authorised for compulsory acquisition under the terms of this Order, will be no less advantageous than it was before such acquisition, to the persons in whom it is vested, other persons, if any, entitled to rights of common or other rights, and the public and that, accordingly, section 132(3)f9 of the 2008 Act applies;

Accordingly, the Secretary of State, in exercise of the powers conferred by sections 114, 115, 120f10, 140 and 149A of the 2008 Act, makes the following Order—

Annotations to the whole text

Footnotes

f1

2008 c. 29. Section 37 was amended by Chapter 6 and Part 6 of, and Schedule 13 to, the Localism Act 2011 (c. 20).

f2

S.I. 2009/2264.

f3

Section 61 was amended by section 128(2) and Schedule 13, paragraph 18 to the Localism Act 2011 c. 20 and by section 26 of the Infrastructure Act 2015 c. 7.

f4

Section 65 was amended by Schedule 13 paragraph 22(2) and Schedule 25, paragraph 1 to the Localism Act 2011 c. 20 and by section 27(1) of the Infrastructure Act 2015 c. 7.

f5

S.I. 2010/103, amended by S.I. 2012/635.

f6

Section 74 was amended by the Localism Act 2011 (c. 20) section 128(2) and 237, Schedule 13 paragraph 29 and Schedule 25, Part 20.

f7

S.I. 2017/572.

f8

Section 104 was amended by section 58(5) of the Marine and Coastal Access Act 2009 (c. 23) and by section 128(2) and Schedule 13, paragraphs 1 and 49(1) to (6) of the Localism Act 2011 c. 20.

f9

Section 132 was amended by section 24(3) of the Growth and Infrastructure Act 2013 (c. 27).

f10

Sections 114, 115 and 120 were amended by sections 128(2) and 140 and Schedule 13, paragraphs 1, 55(1), (2) and 60(1) and (3) of the Localism Act 2011. Relevant amendments were made to section 115 by section 160(1) to (6) of the Housing and Planning Act 2016 (c. 22).

Contents

  1. Part 1: PRELIMINARY
  2. 1Citation and commencement
  3. 2Interpretation
  4. 3Electronic communications
  5. Part 2: PRINCIPAL POWERS
  6. 4Development consent etc. granted by this Order
  7. 5Maintenance of authorised development
  8. 6Operation of authorised development
  9. 7Benefit of this Order
  10. 8Consent to transfer benefit of this Order
  11. 9Amendment and modification of statutory provisions
  12. Part 3: STREETS
  13. 10Power to alter layout etc. of streets
  14. 11Street works
  15. 12Construction and maintenance of new or altered means of access
  16. 13Temporary stopping up of streets, public rights of way and access land
  17. 14Access to works
  18. 15Agreements with streets authorities
  19. 16Traffic regulation
  20. Part 4: SUPPLEMENTAL POWERS
  21. 17Discharge of water
  22. 18Felling or lopping of trees and removal of hedgerows
  23. 19Protective works to buildings
  24. 20Authority to survey and investigate the land
  25. 21Removal of human remains
  26. Part 5: POWERS OF ACQUISITION
  27. 21ASupplemental land
  28. 22Compulsory acquisition of land
  29. 23Power to override easements and other rights
  30. 24Time limit for exercise of authority to acquire land compulsorily
  31. 25Compulsory acquisition of rights etc.
  32. 26Private rights
  33. 27Application of the 1981 Act
  34. 28Acquisition of subsoil and airspace only
  35. 29Modification of Part 1 of the 1965 Act
  36. 30Rights under or over streets
  37. 31Temporary use of land for carrying out the authorised development
  38. 32Temporary use of land for maintaining the authorised development
  39. 33Statutory undertakers
  40. 34Apparatus and rights of statutory undertakers in streets
  41. 35Recovery of costs of new connections
  42. 36Compulsory acquisition of land – incorporation of the mineral code
  43. Part 6: MISCELLANEOUS AND GENERAL
  44. 37Deemed marine licence
  45. 38Application of landlord and tenant law
  46. 39Operational land for purposes of the 1990 Act
  47. 40Defence to proceedings in respect of statutory nuisance
  48. 41Protection of interests
  49. 42Saving for Trinity House
  50. 43Crown Rights
  51. 44Procedure in relation to certain approvals
  52. 45Certification of plans etc.
  53. 46Service of notices
  54. 47Arbitration
  55. 48Funding for compulsory acquisition compensation
  56. Signature
  57. Schedule 1: AUTHORISED DEVELOPMENT
  58. Schedule 2: REQUIREMENTS
  59. 1Commencement of the authorised development
  60. 2Notice of start and completion of commissioning
  61. 3Detailed design
  62. 4Landscape and biodiversity protection management and enhancement
  63. 5Public rights of way and access land management
  64. 6External lighting
  65. 7Highway accesses
  66. 8Means of enclosure
  67. 9Site security
  68. 10Fire prevention
  69. 11Surface and foul water drainage
  70. 12Flood risk mitigation
  71. 13Contaminated land and groundwater
  72. 14Archaeology
  73. 15Protected species
  74. 16Construction environmental management plan
  75. 17Protection of highway surfaces
  76. 18Construction traffic management plan
  77. 19Construction workers travel plan
  78. 20Construction hours
  79. 21Control of noise - construction
  80. 22Control of noise - operation
  81. 23Piling and penetrative foundation design
  82. 24Waste management on site - construction wastes
  83. 25Restoration of land used temporarily for construction
  84. 26Combined heat and power
  85. 27Aviation warning lighting
  86. 28Air safety
  87. 29Local liaison group
  88. 30Employment, skills and training plan
  89. 31Carbon dioxide capture transfer and storage
  90. 32Decommissioning
  91. 33Requirement for written approval
  92. 34Approved details and amendments to them
  93. 35Amendments agreed by the relevant planning authority
  94. 36Consultation with South Tees Development Corporation
  95. 37Effluent nutrient nitrogen safeguarding scheme
  96. 38Consultation with Sembcorp and TG entities
  97. Schedule 3: AMENDMENTS OF THE YORK POTASH HARBOUR FACILITIES ORDER 2016
  98. 1Paragraph 1
  99. 2Paragraph 2
  100. 3Paragraph 3
  101. Schedule 4: STREETS SUBJECT TO STREET WORKS
  102. Schedule 5: ACCESS
  103. 1THOSE PARTS OF THE ACCESSES TO BE MAINTAINED BY THE HIGHWAY AUTHORITY
  104. 2THOSE PARTS OF THE ACCESSES TO BE MAINTAINED BY THE STREET AUTHORITY
  105. Schedule 6: TEMPORARY STOPPING UP OF STREETS, PUBLIC RIGHTS OF WAY AND ACCESS LAND
  106. 1THOSE PARTS OF THE STREET TO BE TEMPORARILY STOPPED UP
  107. 2THOSE PUBLIC RIGHTS OF WAY TO BE TEMPORARILY STOPPED UP
  108. 3THOSE PARTS OF THE ACCESS LAND WHERE PUBLIC ACCESS MAY BE TEMPORARILY SUSPENDED
  109. Schedule 7: LAND IN WHICH NEW RIGHTS ETC. MAY BE ACQUIRED
  110. 1Interpretation
  111. Schedule 8: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF NEW RESTRICTIVE COVENANTS
  112. Compensation enactments
  113. 1Paragraph 1
  114. 2Paragraph 2
  115. 3Paragraph 3
  116. Application of Part 1 of the 1965 Act
  117. 4Paragraph 4
  118. 5Paragraph 5
  119. Schedule 9: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
  120. Schedule 10: DEEMED MARINE LICENCE UNDER THE 2009 ACT: PROJECT A
  121. Part 1: LICENSED ACTIVITIES
  122. 1Paragraph 1
  123. 2Details of licensed activities
  124. 3Details of licensed activities
  125. 4Details of licensed activities
  126. 5Details of licensed activities
  127. 6Details of licensed activities
  128. 7Details of licensed activities
  129. 8Details of licensed activities
  130. Part 2: CONDITIONS
  131. 9General
  132. 10Notifications and Inspections
  133. 11Pre-construction
  134. 12Pre-construction
  135. 13Pre-construction
  136. 14Reporting of engaged agents, contractors and vessels
  137. 15Written scheme of archaeological investigation
  138. 16Construction, Operation and Maintenance
  139. 17Construction, Operation and Maintenance
  140. 18Construction, Operation and Maintenance
  141. 19Construction, Operation and Maintenance
  142. 20Construction, Operation and Maintenance
  143. 21Construction, Operation and Maintenance
  144. 22UXO Clearance
  145. 23Post Construction
  146. 24Disposal
  147. 25Disposal
  148. 26Disposal
  149. 27Disposal
  150. 28Provision of Information
  151. 29Amendments to plans etc.
  152. 30Maximum parameters
  153. 31Safety Management
  154. 32Provision of Information
  155. Schedule 11: DEEMED MARINE LICENCE UNDER THE 2009 ACT: PROJECT B
  156. Part 1: LICENSED ACTIVITIES
  157. 1Paragraph 1
  158. 2Details of licensed activities
  159. 3Details of licensed activities
  160. 4Details of licensed activities
  161. 5Details of licensed activities
  162. 6Details of licensed activities
  163. 7Details of licensed activities
  164. 8Details of licensed activities
  165. Part 2: CONDITIONS
  166. 9General
  167. 10Notifications and Inspections
  168. 11Pre-construction
  169. 12Pre-construction
  170. 13Pre-construction
  171. 14Reporting of engaged agents, contractors and vessels
  172. 15Written scheme of archaeological investigation
  173. 16Construction, Operation and Maintenance
  174. 17Construction, Operation and Maintenance
  175. 18Construction, Operation and Maintenance
  176. 19Construction, Operation and Maintenance
  177. 20Construction, Operation and Maintenance
  178. 21Construction, Operation and Maintenance
  179. 22UXO Clearance
  180. 23Post Construction
  181. 24Disposal
  182. 25Disposal
  183. 26Disposal
  184. 27Disposal
  185. 28Provision of Information
  186. 29Amendments to plans etc.
  187. 30Maximum parameters
  188. 31Safety Management
  189. 32Provision of Information
  190. Schedule 12: PROTECTIVE PROVISIONS
  191. Part 1: FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
  192. 1Paragraph 1
  193. 2Paragraph 2
  194. 3Precedence of the 1991 Act in respect of apparatus in the streets
  195. 4Precedence of the 1991 Act in respect of apparatus in the streets
  196. 5No acquisition etc. except by agreement
  197. 6Removal of apparatus
  198. 7Facilities and rights for alternative apparatus
  199. 8Retained Apparatus
  200. 9Expenses and costs
  201. 10Expenses and costs
  202. 11Enactments and agreements
  203. Part 2: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
  204. 12Paragraph 12
  205. 13Paragraph 13
  206. 14Paragraph 14
  207. 15Paragraph 15
  208. 16Paragraph 16
  209. Part 3: FOR THE PROTECTION OF NATIONAL GRID ELECTRICITY TRANSMISSION AS ELECTRICITY UNDERTAKER
  210. 17Application
  211. 18Interpretation
  212. 19On Street Apparatus
  213. 20Apparatus of National Grid in streets subject to temporary stopping up
  214. 21Protective works to buildings
  215. 22Removal of apparatus
  216. 23Facilities and rights for alternative apparatus
  217. 24Retained apparatus
  218. 25Expenses
  219. 26Indemnity
  220. 27Enactments and agreements
  221. 28Co-operation
  222. 29Access
  223. 30Arbitration
  224. 31Notices
  225. Part 4: FOR THE PROTECTION OF NATIONAL GAS TRANSMISSION PLC AS GAS UNDERTAKER
  226. 32Application
  227. 33Interpretation
  228. 34On Street Apparatus
  229. 35Apparatus of National Gas in streets subject to temporary stopping up
  230. 36Protective works to buildings
  231. 37Removal of apparatus
  232. 38Facilities and rights for alternative apparatus
  233. 39Retained apparatus
  234. 40Expenses
  235. 41Indemnity
  236. 42Enactments and agreements
  237. 43Co-operation
  238. 44Access
  239. 45Arbitration
  240. 46Notices
  241. Part 5: FOR THE PROTECTION OF AIR PRODUCTS PLC
  242. 47Paragraph 47
  243. 48Paragraph 48
  244. 49Precedence of the 1991 Act in respect of apparatus in streets
  245. 50Precedence of the 1991 Act in respect of apparatus in streets
  246. 51No acquisition etc. except by agreement
  247. 52Removal of apparatus
  248. 53Facilities and rights for alternative apparatus
  249. 54Retained Apparatus
  250. 55Expenses and costs
  251. 56Expenses and costs
  252. 57Enactments and agreements
  253. Part 6: FOR THE PROTECTION OF CATS NORTH SEA LIMITED
  254. 58Paragraph 58
  255. 59Paragraph 59
  256. 60Consent under this Part
  257. 61Consent under this Part
  258. 62Consent under this Part
  259. 63Consent under this Part
  260. 64Compliance with the CATS requirements
  261. 65Compliance with the CATS requirements
  262. 66Monitoring for damage to pipelines
  263. 67Monitoring for damage to pipelines
  264. 68Indemnity
  265. 69Costs
  266. 70Arbitration
  267. Part 7: FOR THE PROTECTION OF CF FERTILISERS UK LIMITED
  268. 71Paragraph 71
  269. 72Paragraph 72
  270. 73Precedence of the 1991 Act in respect of apparatus in streets
  271. 74Precedence of the 1991 Act in respect of apparatus in streets
  272. 75Removal of apparatus/access
  273. 76Facilities and rights for alternative apparatus
  274. 77Retained Apparatus
  275. 78Consent under this Part
  276. 79Consent under this Part
  277. 80Consent under this Part
  278. 81Consent under this Part
  279. 82Consent under this Part
  280. 83Notices
  281. 84Co-operation
  282. 85Expenses and costs
  283. 86Expenses and costs
  284. 87Arbitration
  285. Part 8: FOR THE PROTECTION OF EXOLUM SEAL SANDS LTD AND EXOLUM RIVERSIDE LTD
  286. 88Paragraph 88
  287. 89Paragraph 89
  288. 90Consent of restricted works under this Part
  289. 91Prohibition of acquisition and interference
  290. 92Cathodic protection testing
  291. 93Expenses
  292. 94Indemnity
  293. 95Arbitration
  294. Part 9: FOR THE PROTECTION OF INEOS NITRILES (UK) LIMITED
  295. 96Paragraph 96
  296. 97Paragraph 97
  297. 98Consent under this Part
  298. 99Consent under this Part
  299. 100Consent under this Part
  300. 101Compliance with requirements, etc. applying to the INEOS operations
  301. 102Indemnity
  302. 103Arbitration
  303. Part 10: FOR THE PROTECTION OF MARLOW FOODS LIMITED
  304. 104Paragraph 104
  305. 105Paragraph 105
  306. 106Regulation of powers
  307. 107Regulation of powers
  308. 108Co-operation
  309. 109Indemnity
  310. 110Arbitration
  311. Part 11: FOR THE PROTECTION OF RAILWAY INTERESTS
  312. 111Paragraph 111
  313. 112Paragraph 112
  314. 113Paragraph 113
  315. 114Paragraph 114
  316. 115Paragraph 115
  317. 116Paragraph 116
  318. 117Paragraph 117
  319. 118Paragraph 118
  320. 119Paragraph 119
  321. 120Paragraph 120
  322. 121Paragraph 121
  323. 122Paragraph 122
  324. 123Paragraph 123
  325. 124Paragraph 124
  326. 125Paragraph 125
  327. 126Paragraph 126
  328. 127Paragraph 127
  329. 128Paragraph 128
  330. 129Paragraph 129
  331. 130Paragraph 130
  332. 131Paragraph 131
  333. Part 12: FOR THE PROTECTION OF NORTHERN POWERGRID (NORTHEAST) PLC
  334. 132Paragraph 132
  335. 133Paragraph 133
  336. 134Paragraph 134
  337. 135Paragraph 135
  338. 136Paragraph 136
  339. 137Paragraph 137
  340. 138Paragraph 138
  341. 139Paragraph 139
  342. 140Paragraph 140
  343. 141Paragraph 141
  344. 142Paragraph 142
  345. 143Paragraph 143
  346. 144Paragraph 144
  347. 145Paragraph 145
  348. 146Paragraph 146
  349. 147Paragraph 147
  350. 148Paragraph 148
  351. 149Paragraph 149
  352. 150Paragraph 150
  353. Part 13: FOR THE PROTECTION OF NPL WASTE MANAGEMENT LIMITED
  354. 151Paragraph 151
  355. 152Paragraph 152
  356. 153Consent under this Part
  357. 154Consent under this Part
  358. 155Consent under this Part
  359. 156Consent under this Part
  360. 157Indemnity
  361. 158Arbitration
  362. Part 14: FOR THE PROTECTION OF PD TEESPORT LIMITED
  363. 159Paragraph 159
  364. 160Paragraph 160
  365. 161Regulation of powers
  366. 162Regulation of powers
  367. 163Regulation of powers in relation to Seal Sands Road
  368. 164Regulation of powers in relation to South Gare Road
  369. 165Consent under this Part
  370. 166Consent under this Part
  371. 167Consent under this Part
  372. 168Consent under this Part
  373. 169Consent under this Part
  374. 170Indemnity
  375. 171Arbitration
  376. Part 15: FOR THE PROTECTION OF REDCAR BULK TERMINAL LIMITED
  377. 172Paragraph 172
  378. 173Paragraph 173
  379. 174Regulation of powers
  380. 175Regulation of powers
  381. 176Regulation of powers
  382. 177Interference with Apparatus and Access
  383. 178Consent under this Part
  384. 179Consent under this Part
  385. 180Consent under this Part
  386. 181Consent under this Part
  387. 182Consent under this Part
  388. 183Co-operation
  389. 184Co-operation
  390. 185Indemnity
  391. 186Arbitration
  392. Part 16: FOR THE PROTECTION OF SABIC PETROCHEMICALS UK LIMITED
  393. 187Benefit of protective provisions
  394. 188Interpretation
  395. 189Pipeline survey
  396. 190Authorisation of works details affecting pipelines or protected crossing
  397. 191Authorisation of works details affecting pipelines or protected crossing
  398. 192Paragraph 192
  399. 193Paragraph 193
  400. 194Notice of works
  401. 195Further provisions about works
  402. 196Further provisions about works
  403. 197Further provisions about works
  404. 198Further provisions about works
  405. 199Further provisions about works
  406. 200Monitoring for damage to pipelines
  407. 201Monitoring for damage to pipelines
  408. 202Compliance with requirements, etc. applying to the protected land
  409. 203Access for construction and maintenance
  410. 204Access for construction and maintenance
  411. 205Access for construction and maintenance
  412. 206Insurance
  413. 207Insurance
  414. 208Costs
  415. 209Further protection in relation to the exercise of powers under the Order
  416. 210Further protection in relation to the exercise of powers under the Order
  417. 211Further protection in relation to the exercise of powers under the Order
  418. 212Arbitration
  419. Part 17: FOR THE PROTECTION OF THE SEMBCORP PROTECTION CORRIDOR
  420. 213Extent of this Part
  421. 214Interpretation of this Part
  422. 215Separate approvals by third party owners or operators
  423. 216Removal of apparatus
  424. 217Alternative apparatus
  425. 218Consent under this Part in connection with Sembcorp operations
  426. 219Consent under this Part in connection with Sembcorp operations
  427. 220Consent under this Part in connection with Sembcorp operations
  428. 221Consent under this Part in connection with Sembcorp operations
  429. 222Insurance
  430. 223Expenses
  431. 224Indemnity
  432. 225Participation in community groups
  433. 226Notice of start and completion of commissioning
  434. 227Arbitration
  435. 228Additional Agreement
  436. Part 18: FOR THE PROTECTION OF ANGLO AMERICAN
  437. 229Interpretation
  438. 230Paragraph 230
  439. 231Consent to works in the shared area
  440. 232Co-operation
  441. 233Regulation of works within the shared area
  442. 234Regulation of powers over the shared area
  443. 235Constructability Principles
  444. 236Interface Design Process
  445. 237Design Principles
  446. 238Maintenance and Operational Principles
  447. 239Miscellaneous provisions
  448. 240Indemnity
  449. 241Dispute Resolution
  450. 242Dispute Resolution
  451. 243Dispute Resolution
  452. 244Dispute Resolution
  453. 245Dispute Resolution
  454. 246Dispute Resolution
  455. Part 19: FOR THE PROTECTION OF SUEZ RECYCLING AND RECOVERY UK LIMITED
  456. 247Paragraph 247
  457. 248Paragraph 248
  458. 249Consent under this Part
  459. 250Consent under this Part
  460. 251Consent under this Part
  461. 252Consent under this Part
  462. 253Consent under this Part
  463. 254Co-operation
  464. 255Indemnity
  465. 256Arbitration
  466. Part 20: FOR THE PROTECTION OF SOUTH TEES DEVELOPMENT CORPORATION
  467. 257Paragraph 257
  468. 258Paragraph 258
  469. 259Consent for works
  470. 260Consent for works
  471. 261Paragraph 261
  472. 262Paragraph 262
  473. 263Paragraph 263
  474. 264Co-operation
  475. 265Co-operation
  476. 266Co-operation
  477. 267Expenses
  478. 268Indemnity
  479. 269Provision for diversion works
  480. 270Provision for diversion works
  481. 271Provision for diversion works
  482. 272Provision for diversion works
  483. 273Provision for diversion works
  484. 274Provision for diversion works
  485. 275Provision for diversion works
  486. 276Provision for diversion works
  487. 277Provision for diversion works
  488. 278Provision for diversion works
  489. 279Provision for diversion works
  490. 280Provision for diversion works
  491. 281Provision for diversion works
  492. 282Provision for diversion works
  493. 283Provision for diversion works
  494. 284Provision for diversion works
  495. 285Paragraph 285
  496. 286Arbitration
  497. 287Interpretation
  498. 288Interpretation
  499. Part 21: FOR THE PROTECTION OF THE BREAGH PIPELINE OWNERS
  500. 289Paragraph 289
  501. 290Paragraph 290
  502. 291Consent under this Part
  503. 292Consent under this Part
  504. 293Consent under this Part
  505. 294Compliance with requirements, etc. applying to the Breagh Pipeline and the Breagh Pipeline Operations
  506. 295Indemnity
  507. 296Arbitration
  508. Part 22: FOR THE PROTECTION OF TEESSIDE WINDFARM LIMITED
  509. 297Paragraph 297
  510. 298Paragraph 298
  511. 299Consent under this Part
  512. 300Consent under this Part
  513. 301Consent under this Part
  514. 302Consent under this Part
  515. 303Consent under this Part
  516. 304Indemnity
  517. 305Arbitration
  518. Part 23: FOR THE PROTECTION OF HUNTSMAN POLYURETHANES (UK) LIMITED
  519. 306Benefit of protective provisions
  520. 307Interpretation
  521. 308Pipeline survey
  522. 309Authorisation of works details affecting pipelines or protected crossing
  523. 310Authorisation of works details affecting pipelines or protected crossing
  524. 311Paragraph 311
  525. 312Paragraph 312
  526. 313Notice of works
  527. 314Further provisions about works
  528. 315Further provisions about works
  529. 316Further provisions about works
  530. 317Further provisions about works
  531. 318Further provisions about works
  532. 319Monitoring for damage to pipelines
  533. 320Monitoring for damage to pipelines
  534. 321Compliance with requirements, etc. applying to the protected land
  535. 322Access for construction and maintenance
  536. 323Access for construction and maintenance
  537. 324Access for construction and maintenance
  538. 325Insurance
  539. 326Insurance
  540. 327Costs
  541. 328Further protection in relation to the exercise of powers under the Order
  542. 329Further protection in relation to the exercise of powers under the Order
  543. 330Further protection in relation to the exercise of powers under the Order
  544. 331Arbitration
  545. Part 24: FOR THE PROTECTION OF NAVIGATOR TERMINALS SEAL SANDS LIMITED
  546. 332Paragraph 332
  547. 333Paragraph 333
  548. 334Consent under this Part
  549. 335Consent under this Part
  550. 336Consent under this Part
  551. 337Paragraph 337
  552. 338Indemnity
  553. 339Arbitration
  554. Part 25: FOR THE PROTECTION OF NORTHUMBRIAN WATER LIMITED
  555. 340Paragraph 340
  556. 341Paragraph 341
  557. 342Paragraph 342
  558. 343Paragraph 343
  559. 344Paragraph 344
  560. 345Paragraph 345
  561. 346Paragraph 346
  562. 347Paragraph 347
  563. 348Paragraph 348
  564. 349Paragraph 349
  565. 350Paragraph 350
  566. 351Paragraph 351
  567. Part 26: FOR THE PROTECTION OF NORTHERN GAS NETWORKS LIMITED
  568. 352Application
  569. 353Interpretation
  570. 354Interpretation
  571. 355Apparatus of statutory undertaker in stopped up streets
  572. 356Acquisition of land
  573. 357Removal or diversion of apparatus
  574. 358Facilities and rights for alternative apparatus
  575. 359Retained apparatus: protection
  576. 360Expenses
  577. 361Indemnity
  578. 362Enactments and agreements
  579. 363Co-operation
  580. 364Access
  581. 365Arbitration
  582. 366Works falling outside of development authorised by the Order
  583. 367Cathodic protection testing
  584. Part 27: FOR THE PROTECTION OF NORTH TEES LIMITED, NORTH TEES RAIL LIMITED AND NORTH TEES LAND LIMITED
  585. 368Paragraph 368
  586. 369Paragraph 369
  587. 370Consent under this Part
  588. 371Indemnity
  589. 372Arbitration
  590. 373Apparatus
  591. Part 28: FOR THE PROTECTION OF TEESSIDE GAS & LIQUIDS PROCESSING, TEESSIDE GAS PROCESSING PLANT LIMITED & NORTHERN GAS PROCESSING LIMITED
  592. 374Paragraph 374
  593. 375Paragraph 375
  594. 376Paragraph 376
  595. 377Paragraph 377
  596. 378Paragraph 378
  597. 379Paragraph 379
  598. 380Paragraph 380
  599. 381Paragraph 381
  600. 382Paragraph 382
  601. 383Paragraph 383
  602. 384Paragraph 384
  603. 385Paragraph 385
  604. 386Paragraph 386
  605. 387Paragraph 387
  606. 388Paragraph 388
  607. 389Paragraph 389
  608. 390Paragraph 390
  609. 391Approval Principles: Relevant Works Package A
  610. 392Approval Principles: Relevant Works Package A
  611. 393Approval Principles: Relevant Works Package A
  612. 394Approval Principles: Relevant Works Package A
  613. 395Approval Principles: Relevant Works Package B
  614. 396Approval Principles: Relevant Works Package B
  615. 397Compliance with requirements, etc. applying to the NSMP operations
  616. 398Compliance with requirements, etc. applying to the NSMP operations
  617. 399Compliance with requirements, etc. applying to the NSMP operations
  618. 400Indemnity
  619. 401Arbitration
  620. 402Access to plots 110, 112, 113 or 114
  621. 403Access to plots 110, 112, 113 or 114
  622. 404Access to plots 110, 112, 113 or 114
  623. Schedule 13: PROCEDURE FOR DISCHARGE OF REQUIREMENTS
  624. 405Paragraph 405
  625. 406Applications made under a Requirement
  626. 407Further information and consultation
  627. 408Fees
  628. 409Appeals
  629. Schedule 14: DOCUMENTS AND PLANS TO BE CERTIFIED
  630. Schedule 15: DESIGN PARAMETERS
  631. Explanatory note