Paragraph 230 I1

England, Wales and Scotland

The following definitions apply in this Part of this Schedule—

  • “AA Easements” means the Deed of Grant entered into by Redcar Bulk Terminal Limited and York Potash Processing & Ports Limited dated 6 July 2018 and the Deed of Grant entered into by Redcar Bulk Terminal Limited, York Potash Limited and York Potash Processing & Ports Limited dated 26 June 2019;

  • “Anglo American Specified Works” means so much of the Woodsmith Project as is within the Shared Area;

  • “Anglo American” means the parties with the benefit of the York Potash Order (being Anglo American Woodsmith Limited and Anglo American Crop Nutrients Limited) and Anglo American Woodsmith (Teesside) Limited;

  • “Anglo American Apparatus” means the pipeline, cables, structures which are or are to be owned, occupied or maintained by Anglo American within the Shared Area;

  • “EA Permit” means the environmental permit for the landfill site at Bran Sands given permit number EPR/FB3601GS (formerly Waste Management Licence EAWML60092);

  • “expert” means a person appointed pursuant to paragraph 241(b);

  • “NWL Facility” means the Northumbrian Water Limited Bran Sands Wastewater Treatment Plant;

  • “NZT Apparatus” means the pipeline, cables, structures to be owned, occupied or maintained by the undertaker within the Shared Area;

  • “Parties” means the undertaker and Anglo American;

  • “Plans” includes sections, drawings, specifications design data, software, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of the shared area;

  • “Property Documents” means any leases, licences or other documents by virtue of which Anglo American has an interest in, on or over land;

  • “Respective Projects” means the authorised development and the Woodsmith Project;

  • “Secretary of State” means the Secretary of State for Energy Security and Net Zero or any successor in function;

  • “Shared Area” means the land coloured blue on the Shared Area Plan;

  • “Shared Area 1” means the land comprising plots 222 and 223 on the land plans;

  • “Shared Area 2” means the land comprising plots 252, 252a, 253, 253a, 255, 263, 278, 280, 281, 284, 285, 286, 294, 301, 302, 303, 314, 315, 316, 317, 318, 319, 320, 321, 322, 324, 325, 328, 329, 330, 331, 332, 333, 343 and 541 on the land plans;

  • “Shared Area 3” means the land comprising plots 332, 343, 345 and 347 on the land plans;

  • “Shared Area 4” means the land comprising plots 384, 397, 395, 401 and 405 on the land plans;

  • F1“Shared Area 5” means the land comprising plots 417, 418, 427, 432, 436, 439, 543, 545, 546, 547 and 548 on the land plans;

  • “Shared Area 6” means the land comprising plots 540a and 540d on the land plans;

  • “Shared Area Plan” means the plan which is certified as the Net Zero Teesside Anglo American Shared Area Plan by the Secretary of State under article 45 (certification of plans etc.) for the purposes of this Order;

  • “Specified Works” means so much of the authorised development as is within the Shared Area;

  • “STDC Agreement” means a Deed of Licence and Option entered into between South Tees Development Corporation, York Potash Processing and Ports Limited and Sirius Minerals PLC dated 9 January 2019;

  • “Woodsmith Project” means the construction, operation, or maintenance of development authorised by the York Potash Order or by any planning permission or development consent order issued whether before or after the date of this F2Order as part of the Woodsmith Project such development comprising—

    1. (a)

      an underground mine at Sneatonthorpe for the mining of polyhalite;

    2. (b)

      a Mineral Transport System being a tunnel from the mine to Teesside;

    3. (c)

      a Material Handling Facility at Wilton International, Teesside; and

    4. (d)

      Harbour Facilities at Teesside including an overland conveyor between the Material Handling Facility and the Redcar Bulk Terminal and the harbour authorised by the York Potash Order and planning permissions; and

  • “York Potash Order” means the York Potash Harbour Facilities Order 2016.

Annotations

Textual amendments

F1

Words in Sch. 12 para. 230 substituted (29.10.2025) by virtue of The Net Zero Teesside (Amendment) Order 2025 (S.I. 2025/1143), arts. 1, 17

F2

Word in Sch. 12 para. 230 substituted (21.12.2024) by The Net Zero Teesside (Correction) Order 2024 (S.I. 2024/1384), art. 1, Sch. Table

Commencement

I1

Sch. 12 para. 230 in force at 11.3.2024, see art. 1