Paragraph 153 Consent under this PartI1
England, Wales and Scotland
Before commencing any part of the authorised development which would have an effect on the operation or maintenance of the NPL access shafts or access to them, the undertaker must submit to NPL the works details for the proposed works and such further particulars as NPL may, within 28 days from the day on which the works details are submitted under this paragraph, reasonably require.
Annotations
Commencement
- I1
Sch. 12 para. 153 in force at 11.3.2024, see art. 1