Paragraph 193 I1
In the event that—
authorisation has not been given within 30 days of the undertaker obtaining a written acknowledgment of receipt from a specified person of the further particulars supplied under paragraph 189(2)F1,
approval of the works details is to be deemed to be given and the relevant works may commence.
the undertaker may refer the matter to an arbitrator for determination under paragraph 211.
Where the matter is referred to arbitration under paragraph 192(2) the arbitrator is to determine whether or not authorisation should be given and, if so the conditions which should reasonably be attached to the authorisation under sub-paragraphs (a) and (b) of paragraph 191(1).
Annotations
Textual amendments
- F1
Sch. 12 para. 193(1)(b): comma substituted for full stop (21.12.2024) by The Net Zero Teesside (Correction) Order 2024 (S.I. 2024/1384), art. 1, Sch. Table
Commencement
- I1
Sch. 12 para. 193 in force at 11.3.2024, see art. 1