OpenLegislation

Paragraph 226 Notice of start and completion of commissioningI1

England, Wales and Scotland

(1)

Notice of the intended start of commissioning of the authorised development must be given to Sembcorp no later than fourteen days prior to the date that commissioning is started.

(2)

Notice of the intended date of final commissioning of each of Work Nos. 1 and 6 must be given to Sembcorp no later than fourteen days prior to the date of final commissioning.

Annotations

Commencement

I1

Sch. 12 para. 226 in force at 11.3.2024, see art. 1