Paragraph 7 Highway accessesI1
England, Wales and Scotland
No part of the authorised development may commence, save for the permitted preliminary works, until details of the siting, design and layout (including visibility splays and construction specification) of any new or modified temporary means of access between any part of the Order limits and the public highway to be used by vehicular traffic during construction, and the means of and a programme for reinstating any such means of access after construction has, for that part, been submitted to and, after consultation with the highway authority, Sembcorp and STDC, approved by the relevant planning authority.
The highway accesses approved pursuant to sub-paragraph (1) must be constructed in accordance with the approved details and, unless approved pursuant to sub-paragraph (3) to be retained permanently, reinstated in accordance with the approved programme, unless otherwise agreed with the relevant planning authority.
Prior to the date of final commissioning of each relevant Work No. details of the siting, design and layout (including visibility splays and construction specification) of any new or modified permanent means of access to a highway to be used by vehicular traffic, must, for each part of the authorised development, be submitted to and, after consultation with the highway authority, Sembcorp and STDC, approved by the relevant planning authority.
The highway accesses approved pursuant to sub-paragraph (3) must be constructed in accordance with the details approved unless otherwise agreed with the relevant planning authority.
Annotations
Commencement
- I1
Sch. 2 para. 7 in force at 11.3.2024, see art. 1