Paragraph 8 Means of enclosureI1

England, Wales and Scotland

(1)

No part of the authorised development may commence, save for the permitted preliminary works, until details of a programme for the removal of all temporary means of enclosure for any construction areas or sites associated with the authorised development have, for that part, been submitted to and approved by the relevant planning authority (following consultation with Sembcorp and STDC).

(2)

Any construction areas or sites associated with the authorised development must remain securely fenced at all times during construction and commissioning of the authorised development and the temporary means of enclosure must then be removed in accordance with the programme approved pursuant to sub-paragraph (1).

(3)

Prior to the date of final commissioning of each relevant Work No., details of any proposed permanent means of enclosure, must, for each part of the authorised development, be submitted to and approved by the relevant planning authority.

(4)

Prior to the date of final commissioning of each relevant Work No., any approved permanent means of enclosure must be completed.

(5)

The authorised development must be carried out in accordance with the approved details unless otherwise agreed with the relevant planning authority.

(6)

In this requirement, “means of enclosure” means fencing, walls or other means of boundary treatment and enclosure.

Annotations

Commencement

I1

Sch. 2 para. 8 in force at 11.3.2024, see art. 1