Paragraph 343 I1
England, Wales and Scotland
The alteration, extension, removal or re-location of any apparatus shall not be implemented until—
any requirement for any permits under the Environmental Permitting Regulations 2016 or other replacement legislation and any other associated consents are obtained; and
if applicable, the undertaker has made the appropriate application under sections 106 (right to communicate with public sewers), 112 (requirement that proposed drain or sewer be constructed so as to form part of the general system) or 185 (duty to move pipes, etc. in certain cases) of the Water Industry Act 1991 as may be required by those provisions and has provided a plan of the works proposed to NW and NW has given the necessary consent or approval under the relevant provision, such agreement not to be unreasonably withheld or delayed,
and in the event that such works are to be executed by the undertaker, they are to be executed only in accordance with the plan, section and description submitted and in accordance with such reasonable requirements as may be made by NW for the alteration or otherwise for the protection of the apparatus, or for securing access to it.
Annotations
Commencement
- I1
Sch. 12 para. 343 in force at 11.3.2024, see art. 1