Paragraph 278 Provision for diversion worksI1

England, Wales and Scotland

If the Teesworks entity submits further information to the undertaker within 30 days of receipt of the information notice, the undertaker must consider the further information and paragraph 272 applies again provided that the undertaker is not obliged to consider any further information that is received by the undertaker—

(a)

more than 30 days after the date of the information notice issued by the undertaker under paragraph 272(c); or

(b)

in any case 150 days from the date of the undertaker’s works notice under paragraph 268(b) or if relevant 150 days from the date of any revised works notice issued by the undertaker under paragraph 269.

Annotations

Commencement

I1

Sch. 12 para. 278 in force at 11.3.2024, see art. 1