Paragraph 254 Co-operationI1
England, Wales and Scotland
This paragraph applies insofar as—
the construction of the Suez energy from waste facility and the authorised development may be undertaken within the Order limits concurrently; or
the construction of one of the respective authorised developments would have an effect on the operation or maintenance of the other respective authorised development or access to it.
Where this paragraph applies the undertaker and Suez must—
co-operate with each other with a view to ensuring—
the co-ordination of construction programming and the carrying out of the respective authorised developments;
that access for the purposes of constructing the respective authorised developments is maintained for the undertaker, Suez and their respective employees, contractors and sub-contractors; and
that operation, maintenance and access to the respective authorised developments is maintained for the undertaker and Suez; and
use reasonable endeavours to avoid any conflict arising from the carrying out of the respective authorised developments.