Paragraph 12 Pre-constructionI1
England, Wales and Scotland
The relevant undertaker must submit a CEMP covering the period of construction to include details of—
a marine pollution contingency plan to address the risks, methods and procedures to deal with any spills and collision incidents of the authorised development in relation to all activities to be carried out;
a biosecurity plan detailing how risk of the introduction and spread of invasive non-native species will be minimised;
waste management and disposal arrangements; and
the appointment and responsibilities of a fisheries liaison officer.
The CEMP must be submitted to the MMO for approval in writing at least three months prior to the commencement of the licenced activities or part of the licensed activities.
The CEMP submitted pursuant to sub-paragraph (2) must be in accordance with the framework construction environmental management plan.
The licensed activities must be carried out in accordance with the CEMP approved pursuant to sub-paragraph (2) unless otherwise agreed in writing with the MMO.