Paragraph 23 Post ConstructionI1

England, Wales and Scotland

The relevant undertaker must ensure that any equipment, temporary structures, waste and debris associated with the licensed activities are removed within six weeks of completion of the licensed activity.

Annotations

Commencement

I1

Sch. 10 para. 23 in force at 11.3.2024, see art. 1