Paragraph 299 Consent under this PartI1

England, Wales and Scotland

Before commencing any part of the authorised development which would have an effect on the operation or maintenance of the Teesside Windfarm operations or access to them, or cross any infrastructure owned or operated by Teesside Windfarm, and before commencing the restricted works, the undertaker must submit to Teesside Windfarm the works details for the proposed works and such further particulars as Teesside Windfarm may, within 28 days from the day on which the works details are submitted under this paragraph, reasonably require.

Annotations

Commencement

I1

Sch. 12 para. 299 in force at 11.3.2024, see art. 1