OpenLegislation

Paragraph 150 I1

England, Wales and Scotland

Prior to carrying out any works within the Order limits Northern Powergrid must give written notice of the proposed works to the undertaker, such notice to include full details of the location of the proposed works, their anticipated duration, access arrangements, depths of the works, and any other information that may impact upon the works consented by the Order.

Annotations

Commencement

I1

Sch. 12 para. 150 in force at 11.3.2024, see art. 1