Paragraph 266 Co-operationI1

England, Wales and Scotland

(1)

This paragraph applies insofar as—

(a)

the construction of the authorised development may be undertaken on the Teesworks site concurrently with demolition or site preparation works undertaken by the Teesworks entity;

(b)

the construction of the respective authorised developments may be undertaken on the Teesworks site concurrently; or

(c)

the construction of one of the respective authorised developments would have an effect on the operation or maintenance of the other respective authorised development or access to it.

(2)

Where this paragraph applies the undertaker and the Teesworks entity must—

(a)

co-operate with each other with a view to ensuring—

(i)

the co-ordination of construction programming and the carrying out of the respective authorised developments;

(ii)

that access for the purposes of constructing the respective authorised developments is maintained for the undertaker, the Teesworks entity and their respective employees, contractors and sub-contractors; and

(iii)

that operation, maintenance and access to the respective authorised developments is maintained for the undertaker and the Teesworks entity; and

(b)

use reasonable endeavours to avoid any conflict arising from the carrying out of the respective authorised developments.

Annotations

Commencement

I1

Sch. 12 para. 266 in force at 11.3.2024, see art. 1