Before commencing any part of the authorised development which would have an effect on the operation or maintenance of the Suez energy from waste facility or access to it, the undertaker must submit to Suez the works details for the proposed works and such further particulars as Suez may, within 28 days from the day on which the works details are submitted under this paragraph, reasonably require.

Annotations

Commencement

I1

Sch. 12 para. 250 in force at 11.3.2024, see art. 1