Paragraph 178 Consent under this PartI1
England, Wales and Scotland
Before commencing—
(a)
any part of the authorised development which would have an effect on the RBT operations or access to them; or
(b)
any activities on or to the RBT site,
the undertaker must submit to RBT the works details for the proposed works or activities and such further particulars as RBT may, not less than 28 days from the day on which the works details are submitted under this paragraph, reasonably require.
Annotations
Commencement
- I1
Sch. 12 para. 178 in force at 11.3.2024, see art. 1