Paragraph 359 Retained apparatus: protectionI1
England, Wales and Scotland
Not less than 28 days before commencing the execution of any works that will or may be situated on, over, under or within 15 metres measured in any direction of any apparatus, or (wherever situated) impose any load directly upon any apparatus or involve embankment works within 15 metres of any apparatus, the removal or diversion of which apparatus has not been required by the undertaker under paragraph 356(2) or otherwise or by Northern Gas Networks under paragraph 356(3), the undertaker must submit to Northern Gas Networks a plan showing the works and the apparatus.
The plan to be submitted to Northern Gas Networks under sub-paragraph (1) shall be detailed including a method statement and describing—
the exact position of the works;
the level at which these are proposed to be constructed or renewed;
the manner of their construction or renewal including details of excavation, positioning of plant etc;
the position of all apparatus; and
by way of detailed drawings, every alteration proposed to be made to or close to any apparatus.
Subject to sub-paragraph (4) the undertaker must not commence the construction or renewal of any works to which sub-paragraphs (1) or (2) apply until Northern Gas Networks has given written approval of the plan so submitted.
Any approval of Northern Gas Networks F1... required under sub-paragraph (3)—
may be given subject to reasonable conditions for any purpose mentioned in sub-paragraph (5) or (7); and
must not be unreasonably withheld or delayed.
In relation to works to which sub-paragraph (1) applies, Northern Gas Networks may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its system against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.
Works executed under this Order to which this paragraph 358 applies must be executed only in accordance with the relevant plan, notified under sub-paragraph (1) and approved (with conditions, if applicable) under sub-paragraph (4), as amended from time to time by agreement between the undertaker and Northern Gas Networks. Northern Gas Networks is entitled to watch and inspect the execution of those works.
Where Northern Gas Networks requires any protective works or subsidence monitoring to be carried out either by itself or by the undertaker (whether of a temporary or permanent nature), Northern Gas Networks must give the undertaker notice of such requirement in its approval under sub-paragraph (3), and—
such protective works must be carried out to Northern Gas Networks’ reasonable satisfaction prior to the carrying out of the relevant part of the works;
ground subsidence monitoring must be carried out in accordance with a scheme approved by Northern Gas Networks (such approval not to be unreasonably withheld or delayed), which shall set out—
the apparatus which is to be subject to such monitoring;
the extent of land to be monitored;
the manner in which ground levels are to be monitored;
the timescales of any monitoring activities; and
the extent of ground subsidence which, if exceeded, must require the undertaker to submit for Northern Gas Networks’ approval a ground subsidence mitigation scheme in respect of such subsidence; and
if a subsidence mitigation scheme is required, it must be carried out as approved (such approval not to be unreasonably withheld or delayed).
Nothing in this paragraph shall preclude the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of the relevant works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph shall apply to and in respect of the new plan.
The Undertaker must not be required to comply with sub-paragraphs (1) or (2) in the case of emergency but in that case it must give to Northern Gas Networks notice as soon as is reasonably practicable and a plan of those works shall comply with the other requirements in this paragraph insofar as is reasonably practicable in the circumstances, provided that it always complies with sub-paragraph (10).
At all times when carrying out any works authorised under the Order that may or will affect the apparatus, the Undertaker must comply with the Statutory undertaker’s policies for safe working in proximity to gas apparatus including the “Specification for safe working in the vicinity of Northern Gas Networks, Gas pipelines and associated installation requirements for third parties “NGN/SPSSW22” and the Health and Safety Executive guidance document “HS(G)47 Avoiding Danger from underground services”.
Annotations
Textual amendments
- F1
Word in Sch. 12 para. 359(4) omitted (21.12.2024) by virtue of The Net Zero Teesside (Correction) Order 2024 (S.I. 2024/1384), art. 1, Sch. Table
Commencement
- I1
Sch. 12 para. 359 in force at 11.3.2024, see art. 1