Paragraph 19 Construction workers travel planI1
England, Wales and Scotland As made
No part of the authorised development may commence, save for the permitted preliminary works, until a construction workers travel plan for that part has been submitted to and, after consultation with National Highways and the relevant highway authority and STDC, approved by the relevant planning authority.
The plan submitted and approved must be in accordance with Chapter 16 of the environmental statement and the framework construction workers travel plan.
The plan submitted and approved must include—
measures to promote the use of sustainable transport modes to and from the authorised development by construction staff;
provision as to the responsibility for, and timescales of, the implementation of those measures;
details of parking for construction personnel within the construction sites;
a monitoring and review regime; and
the profile of activity across the day.
The approved plan must be implemented within three months of commencement of the relevant part of the authorised development and must be maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.