Schedule 9 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1
England, Wales and Scotland
Table 8
(1) Plot numbers shown on Land Plans | (2) Purpose for which temporary possession may be taken |
|---|---|
| 289, 292, 293, 298, 300, 336, 337, 338, 342 | Temporary use as laydown, construction compound, construction use and accesses (Work No. 9A) required to facilitate construction of the authorised development |
| 67, 67a, 68, 122, 125 | Temporary use as laydown, construction compound, construction use and accesses (Work Nos. 9C and 9D) required to facilitate construction of Work No. 2A |
If WN9C— 122, 125 If WN9D— 67, 67a, 68 | Temporary use as laydown, construction compound, construction use and accesses (Work Nos. 9C and 9D) required to facilitate construction of Work No. 2B |
| 19, 48, 49, 50, 51, 52, 53, 54, 55, 64, 67, 67a, 68, 122, 125, 174c, 179, 179a, 193, 195, 197, 199, 202a | Temporary use as laydown, construction compound, construction use and accesses (Work Nos. 9B, 9C, 9D, 9E and 9F) required to facilitate construction of Work No. 6 |
| 222, 223, 282, 283, 287, 290, 291, 296, 299, 348, 362, 363, 367, 370, 373, 374, 376, 381, 393a, 393d, 393e | Temporary use to facilitate access to and highway improvements (Work No. 10) in relation to the authorised development |
| 48, 49, 50, 51, 52, 53, 54, 55, 64, 123, 188, 189 | Temporary use to facilitate access to and highway improvements (Work No. 10) in relation to Work Nos. 2A, 2B and 6 |
| 393a, 393d, 393e | Temporary use to facilitate carrying out of Work No. 3A |
| 1a, 2a, 3a, 4a, 6a, 7a, 7b, 8a, 8b, 9a, 10a, 12a, 13a, 15a, 17, 20, 22a, 23a, 28a, 34a 39a, 39b, 43a, 47a, 63a, 66a, 70a, 70b, 90a, 94a, 94b, 100a, 100b, 124a, 124b, 128a, 135, 138a, 141a, 142a, 156a, 157a, 158a, 166a, 169a, 171a, 172a, 174a, 174b, 176a, 183a, 184a, 185a, 185b, 190a, 191c, 192 | Temporary use to facilitate carrying out of Work No. 6 |
Annotations
Commencement
- I1
Sch. 9 in force at 11.3.2024, see art. 1