Paragraph 33 Notification, approval, protective works

Original text. Later amendments are not shown.

Network Rail must give to the engineer 14 days’ notice of its intention to commence the construction of any of the specified or protective works (unless otherwise agreed in writing by Network Rail and the Trust), save in the case of an emergency in which case Network Rail must give such notice as may be reasonably practicable.