Paragraph 34 Carrying out specified works and protective works

Original text. Later amendments are not shown.

(1)

Any specified works or protective works must, when commenced, be constructed—

(a)

without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled in accordance with this Part of this Schedule and with any requirements made under paragraph 32(3);

(b)

under the supervision (if given) and to the reasonable satisfaction of the engineer;

(c)

in such manner as to cause as little detriment as is reasonably practicable; and

(d)

in such manner as to cause as little inconvenience as is reasonably practicable to the Trust, its officers and agents and all other persons lawfully using the watercourse, except to the extent that temporary obstruction has otherwise been agreed by the Trust.

(2)

Nothing in this Order authorises Network Rail to make or maintain any permanent works in or over the watercourse which will reduce the dimensions of the watercourse other than with the written consent of the Trust.

(3)

Following the completion of the construction of the specified works Network Rail must restore the watercourse to a condition no less satisfactory than its condition immediately prior to the commencement of those works.