The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022
S.I. 2022/1406 · Made 21 December 2022
Transport And Works, England
Transport, England
Made 21st December 2022
Coming into force 11th January 2023
The Secretary of State caused an inquiry to be held for the purposes of the application pursuant to section 11 of the 1992 Act.
The Secretary of State, having considered the objections made and not withdrawn and the report of the person who held the inquiry, has determined to make an Order giving effect to the proposals comprised in the application with modifications which in the opinion of the Secretary of State do not make any substantial change in the proposals.
Notice of the Secretary of State’s determination will be published in the London Gazette on 6th January 2023.
The Secretary of State, in exercise of the powers conferred by sections 1 and 5 of, and paragraphs 1 to 5, 7, 8, 10, 11 and 15 to 17 of Schedule 1 to, the 1992 Act makes the following Order:—
Annotations to the whole text
Footnotes
- f1
-
S.I. 2006/1466, as amended by S.I. 2010/439, S.I. 2011/556, S.I. 2011/2085, S.I. 2012/147, S.I. 2012/1658, S.I. 2012/2590, S.I. 2013/755, S.I. 2014/469, S.I. 2015/627, S.I. 2017/979, S.I. 2017/1070 and S.I. 2019/311.
- f2
-
1992 c. 42. Section 1 was amended by paragraphs 51 and 52 of Schedule 2 to the Planning Act 2008 (c. 29). Section 5 was amended by S.I. 2012/1659.
Contents
- Part 1: PRELIMINARY
- 1Citation and commencement
- 2Interpretation
- 3Incorporation of the Railway Clauses Act
- 4Application of the 1991 Act
- 5Disapplication of legislative provisions
- Part 2: WORKS PROVISIONS
- Principal Powers
- 6Power to construct and maintain works
- 7Power to deviate
- Level Crossings
- 8Level crossings to be stopped up
- Streets
- 9Power to alter layout etc., of streets
- 10Power to execute street works
- 11Temporary stopping up of streets
- 12Construction and maintenance of new or altered highways
- 13Access to works
- 14Use of private roads for construction and operation
- 15Agreements with street authorities
- Supplemental Powers
- 16Discharge of water
- 17Protective works to buildings
- 18Power to survey and investigate land
- Part 3: ACQUISITION AND POSSESSION OF LAND
- Powers of Acquisition
- 19Power to acquire land
- 20Application of Part 1 of the 1965 Act
- 21Application of the 1981 Act
- 22Power to acquire new rights
- 23Power to acquire subsoil or airspace only
- 24Rights under or over streets
- Temporary possession of land
- 25Temporary use of land for construction of works
- 26Temporary use of land for maintenance works
- 27Temporary use of land for access
- Compensation
- 28Disregard of certain interest and improvements
- Supplementary
- 29Extinction or suspension of private rights of way
- 30Time limit for exercise of powers of acquisition
- Part 4: MISCELLANEOUS AND GENERAL
- 31Powers to transfer undertaking
- 32Defence to proceedings in respect of statutory nuisance
- 33Power to lop trees overhanging the authorised works
- 34Power to operate and use railway
- 35Planning permission and supplementary powers
- 36Public open space
- 37Obstruction of construction of authorised works
- 38Disclosure of confidential information
- 39Statutory undertakers etc.
- 40Certification of plans etc.
- 41Service of notices
- 42Protection of interests
- 43No double recovery
- 44Arbitration
- Signature
- Schedule 1SCHEDULED WORKS
- Schedule 2ANCILLARY ACQUISITION OF LAND
- Schedule 3LAND IN WHICH ONLY NEW RIGHTS ETC., MAY BE ACQUIRED
- Schedule 4LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- Schedule 5CLOSURE OF LEVEL CROSSINGS
- Schedule 6STREETS SUBJECT TO ALTERATION OF LAYOUT
- Schedule 7STREETS SUBJECT TO STREET WORKS
- Schedule 8STREETS TO BE TEMPORARILY STOPPED UP OR DIVERTED
- Schedule 9ACCESS TO WORKS
- Schedule 10: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
- Compensation enactments
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- Application of Part 1 of the 1965 Act
- 4Paragraph 4
- 5Paragraph 5
- Schedule 11: PROVISIONS RELATING TO STATUTORY UNDERTAKERS ETC. ON LAND ACQUIRED
- Apparatus of statutory undertakers etc. on land acquired
- 1Paragraph 1
- Schedule 12: PROTECTIVE PROVISIONS
- Part 1: FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
- 1Application
- 2Application
- 3Application
- 4Interpretation
- 5Acquisition of apparatus
- 6Alternative apparatus
- 7Alternative apparatus
- 8Existing apparatus: protection and access
- 9Expenses
- 10Damage to apparatus: costs, losses, etc.
- 11Enactments and agreements
- Part 2: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- Part 3: FOR THE PROTECTION OF DRAINAGE AUTHORITIES AND THE ENVIRONMENT AGENCY
- 16Paragraph 16
- 17Paragraph 17
- 18Paragraph 18
- 19Paragraph 19
- 20Paragraph 20
- 21Paragraph 21
- 22Paragraph 22
- 23Paragraph 23
- 24Paragraph 24
- 25Paragraph 25
- 26Paragraph 26
- Part 4: PROTECTIVE PROVISION FOR THE HOBSON’S CONDUIT TRUST
- 27Application
- 28Interpretation
- 29Exercise of Powers
- 30Exercise of Powers
- 31Survey of watercourse
- 32Notification, approval, protective works
- 33Notification, approval, protective works
- 34Carrying out specified works and protective works
- 35Carrying out specified works and protective works
- 36Carrying out specified works and protective works
- 37Access
- 38Maintenance of the specified works and protective works
- 39Expenses
- 40Detriment to the watercourse
- 41Disputes
- Part 5: FOR THE PROTECTION OF CADENT GAS LIMITED
- 42Application
- 43Interpretation
- 44Interpretation
- 45Interpretation
- 46Interpretation
- 47Interpretation
- 48Interpretation
- 49Interpretation
- 50Interpretation
- 51Interpretation
- 52Interpretation
- 53Interpretation
- 54Interpretation
- 55Interpretation
- 56Interpretation
- 57Interpretation
- Part 6: FOR THE PROTECTION OF CAMBRIDGESHIRE COUNTY COUNCIL IN RESPECT OF THE GUIDED BUSWAY
- 58Application
- 59Application
- 60Interpretation
- 61Interpretation
- 62Guided busway property: notification, protective works
- 63Guided busway property: notification, protective works
- 64Carrying out protective works and specified works
- 65Access
- 66Access
- 67Damage to guided busway property: costs, losses etc.
- 68Expenses
- 69Maintenance of the specified works
- 70Assessment of sums payable
- 71Agreements
- 72Transfer of undertaking
- 73Certified documents
- 74Disputes
- Part 7: FOR THE PROTECTION OF SOUTH STAFFORDSHIRE WATER PLC
- 75Application
- 76Application
- 77Application
- 78Interpretation
- 79Acquisition of apparatus
- 80Alternative apparatus
- 81Alternative apparatus
- 82Existing apparatus: protection and access
- 83Expenses
- 84Damage to apparatus: costs, losses, etc.
- 85Enactments and agreements
- Explanatory note