Regulation 8 Class C: renewable power stations created from class B hereditamentsI1
England and Wales
Class C consists of any hereditament in relation to which the conditions in paragraph (2) are fulfilled.
The conditions mentioned in paragraph (1) are that—
the hereditament is a renewable power station;
the hereditament is first entered onto a F1list on or after 1st April 2013;
the rateable value for the hereditament is greater than the notional baseline; and
the hereditament is an altered hereditament or a new hereditament to which Schedule 1 or 2 applies.
For the purposes of this regulation, the notional baseline is—
for a day falling within the period beginning with 1st April 2018 and ending with 31st March 2024, the amount calculated in accordance with the formula—
where—
X is the notional 31st March 2013 rateable value in respect of the hereditament determined in accordance with Schedule 1 or 2 (as the case may be);
Y is the rateable value shown for the hereditament in the list for 1st April 2017;
Y1 is the rateable value shown for the hereditament in the list for 31st March 2017;
for a day falling within the period beginning with 1st April 2024 and ending with 31st March 2026, the amount calculated in accordance with the formula—
where—
X1 is the notional baseline for 31st March 2024;
Y2 is the rateable value shown for the hereditament in the list for 1st April 2023;
Y3 is the rateable value shown for the hereditament in the list for 31st March 2023;
for a day on or after 1st April 2026, the amount calculated in accordance with the formula—
where—
J is the notional baseline for the last day on which the list immediately preceding the current list was in force;
Z is the rateable value shown for the hereditament in the list for the day on which the current list was compiled;
Z1 is the rateable value shown for the hereditament in the list for the last day on which the list immediately preceding the current list was in force.
For a hereditament to which regulation 19 (change in rateable value F5...) applies, this regulation has effect subject to the modification made by that provision.
In this regulation, “list” means a local non-domestic rating list for the area of a billing authority in England which shows the hereditament concerned.
Annotations
Textual amendments
- F1
Word in reg. 8(2)(b) substituted (1.4.2024) by The Non-Domestic Rating (Rates Retention and Renewable Energy Projects) (Amendment) Regulations 2024 (S.I. 2024/184), regs. 1(2), 6(2)(a)
- F2
Reg. 8(2)(c) substituted (1.4.2024) by The Non-Domestic Rating (Rates Retention and Renewable Energy Projects) (Amendment) Regulations 2024 (S.I. 2024/184), regs. 1(2), 6(2)(b)
- F3
Reg. 8(2A) inserted (1.4.2024) by The Non-Domestic Rating (Rates Retention and Renewable Energy Projects) (Amendment) Regulations 2024 (S.I. 2024/184), regs. 1(2), 6(3)
- F4
Reg. 8(3) inserted (14.12.2017) by The Non-Domestic Rating (Renewable Energy Projects) (Amendment) Regulations 2017 (S.I. 2017/1132), regs. 1, 4(b)
- F5
Words in reg. 8(3) omitted (1.4.2024) by virtue of The Non-Domestic Rating (Rates Retention and Renewable Energy Projects) (Amendment) Regulations 2024 (S.I. 2024/184), regs. 1(2), 6(4)
- F6
Reg. 8(4) inserted (1.4.2024) by The Non-Domestic Rating (Rates Retention and Renewable Energy Projects) (Amendment) Regulations 2024 (S.I. 2024/184), regs. 1(2), 6(5)
Commencement
- I1
Reg. 8 in force at 18.2.2013, see reg. 1(1)