OpenLegislation

Paragraph 29 Onshore decommissioningI1

England and Wales

(1)

Within six months of the permanent cessation of commercial operation of the onshore transmission works an onshore decommissioning plan must be submitted to the relevant planning authority for approval.

(2)

The onshore decommissioning plan must be implemented as approved.

(3)

The undertaker must notify the relevant planning authority in writing of the permanent cessation of commercial operation of the onshore transmission works within 28 days of such permanent cessation.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 29 in force at 1.1.2022, see art. 1