Part 3 Requirements

England and Wales

  1. 1Time limits
  2. 2Detailed offshore design parameters
  3. 3Detailed offshore design parameters
  4. 4Detailed offshore design parameters
  5. 5Detailed offshore design parameters
  6. 6Detailed offshore design parameters
  7. 7Detailed offshore design parameters
  8. 8Detailed offshore design parameters
  9. 9Detailed offshore design parameters
  10. 10Detailed offshore design parameters
  11. 11Detailed offshore design parameters
  12. 12Aviation safety
  13. 13Ministry of Defence surveillance operations
  14. 14Offshore decommissioning
  15. 15Scenarios, stages, and phases of authorised development onshore
  16. 16Detailed design parameters onshore
  17. 17Landfall method statement
  18. 18Provision of landscaping
  19. 19Implementation and maintenance of landscaping
  20. 20Code of construction practice
  21. 21Traffic
  22. 22Highway accesses
  23. 23Archaeological written scheme of investigation
  24. 24Ecological management plan
  25. 25Watercourse crossings
  26. 26Construction hours
  27. 27Control of noise during operational phase and during maintenance
  28. 28European protected species onshore
  29. 29Onshore decommissioning
  30. 30Requirement for written approval
  31. 31Amendments to approved details
  32. 32Operational drainage plan
  33. 33Skills and employment strategy
  34. 34Cromer Primary Surveillance Radar
  35. 35Reuse of temporary works in the event of scenario 1
  36. 36Base port(s) travel plans