In the event that any temporary works which have been constructed pursuant to any development consent order that may be made by the Secretary of State in relation to the Norfolk Vanguard Offshore Wind Farm are proposed to be reused by the undertaker in connection with the authorised project, such reuse may not commence until a scheme which accords with paragraph (2) has been submitted to and approved by the relevant planning authority.

(2)

The scheme to be submitted for approval under paragraph (1) must include details of the temporary works to be reused and a timetable for their reuse;

(3)

The scheme must be implemented as approved.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 35 in force at 1.1.2022, see art. 1