The total length of the cables and the area and volume of their cable protection must not exceed the individual distributions set out in Table 2 of the outline scour protection and cable protection plan and must not exceed the following—

WorkLengthCable protection (m3)Cable protection (m2)
Work No. 3A (Interconnector link)90 kilometres17,000 m334,000 m2
Work No. 4A and 4B (export cable)500 kilometres69,236m3124,086m2