Paragraph 3 Detailed offshore design parametersI1

England, Wales and Scotland

(1)

The total number of wind turbine generators forming part of the authorised project must not exceed F1145 and must be configured such that at any time—

(a)

no more than two-thirds of the total number of wind turbine generators (rounded to the nearest whole number) must be located in Norfolk Vanguard West; and

(b)

no more than one-half of the total number of wind turbine generators (rounded to the nearest whole number) must be located in Norfolk Vanguard East.

(2)

The total number of offshore electrical platforms forming part of the authorised project must not exceed two.

(3)

The total number of accommodation platforms must not exceed two.

(4)

The total number of meteorological masts must not exceed two.

(5)

The total number of LIDAR measurement buoys must not exceed two and the total number of wave measurement buoys must not exceed two.