Paragraph 3 Phasing of the authorised schemeI1
England, Wales and Scotland
Taken together with works authorised and proposed to be constructed pursuant to licence 2 (transmission)—
the total number of offshore electrical platforms forming part of the authorised scheme must not exceed two;
the total amount of scour protection for the offshore electrical platforms forming part of the authorised scheme must not exceed 20,000m2 and 100,000 m3; and
the total amount of inert material of natural origin disposed within the offshore Order limits as part of the authorised scheme must not exceed 11,475,000 m3;
the total amount of disposal for drill arisings in connection with any foundation drilling must not exceed 14,137m3;
the total length of cable and the amount of cable protection must not exceed the figures stated in condition 2 of this licence; and
in the Haisborough, Hammond and Winterton Special Area of Conservation, the total area of cable protection must not exceed 32,000m² and the total volume of cable protection must not exceed 20,800m³.
Prior to the commencement of the authorised scheme the undertaker must give notice to the MMO detailing—
whether the authorised scheme will be constructed—
in a single offshore phase under this licence; or
in two offshore phases under this licence and licence 2 (transmission); and
where the authorised scheme will be constructed in two offshore phases, the total number of offshore electrical platforms to be constructed in each phase.
Annotations
Commencement
- I1
Sch. 11 Pt. 4 para. 3 in force at 5.3.2022, see art. 1