Paragraph 17 Unexploded ordnance (UXO) survey
(1)
No part of the authorised development may commence until a survey to ascertain UXO risk on the construction site is carried out and submitted to the relevant planning authority and the MMO together with (if required) any proposals of the undertaker to mitigate the risks and to adhere to the recommendations included in the UXO report.
(2)
The authorised development must thereafter be carried out fully in accordance with such recommendations of the UXO report as are agreed by the undertaker and the relevant planning authority.