Paragraph 26 Construction of Work Nos. 6a and 6bI1

England, Wales and Scotland

(1)

No construction of Work Nos. 6a and 6b shall be carried out until a strategy to mitigate effects from construction of those works on the North Killingholme Haven Pits has been submitted to and approved by the relevant planning authority, in consultation with Natural England.

(2)

The strategy shall include—

(a)

details of a construction programme to ensure that piling construction activities are carried out only from January to March in any calendar year;

(b)

details of the measures to be taken to screen construction activities from the North Killingholme Haven Pits, including—

(i)

the construction of a hoarding along the southern boundary of the route of the construction works to reduce noise and visual disturbance to birds in the North Killingholme Haven Pits; and

(ii)

where possible, the retention of the existing hedgerow located between the southern boundary of the order limits and the North Killingholme Haven Pits; and

(c)

details of directional construction lighting to minimise light spill to the North Killingholme Haven Pits.

(3)

Construction of Work Nos. 6a and 6b shall be carried out in accordance with the approved strategy.