Paragraph 5 Removal of apparatusI1
England, Wales and Scotland
If, the undertaker acquires or overrides any interest in any land in which apparatus is laid, the apparatus shall not be removed under this Part of this Schedule and any right of Centrica to maintain the apparatus in that land shall not be extinguished until alternative apparatus has been constructed at the undertaker’s expense, and is in operation to the reasonable satisfaction of Centrica in accordance with sub-paragraph (2) to (5).
If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of apparatus in that land, it shall give to Centrica 56 days’ advance written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order Centrica reasonably needs to remove the apparatus) the undertaker shall, subject to sub-paragraph (3), afford to Centrica to their satisfaction (taking into account paragraph 6(1) below) the necessary facilities and rights for—
the construction of an alternative apparatus in other land of the undertaker or Centrica; and
subsequently for the maintenance of that apparatus.
If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker or Centrica, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, Centrica shall, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation shall not extend to the requirement for Centrica to seek compulsory purchase powers to this end unless it elects to so do.
Any alternative apparatus to be constructed in land of the undertaker or Centrica under this Part of this Schedule shall be constructed in such manner and in such line or situation as may be agreed between Centrica and the undertaker.
Centrica shall, after the alternative apparatus to be provided or constructed has been agreed, and subject to the grant to Centrica of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay, at the cost of the undertaker, to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this Part of this Schedule.
If works pursuant to sub-paragraph (1) include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on Centrica any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, such sum shall be paid to the undertaker by the amount which represents that benefit.
Annotations
Commencement
- I1
Sch. 8 Pt. 5 para. 5 in force at 2.10.2014, see art. 1