Paragraph 21 Decommissioning and demolition of the electricity and heat generating stationI1
England, Wales and Scotland
Within 24 months of the electricity and heat generating station comprising Works No. 1a ceasing to be used for waste management purposes, a plan for the decommissioning, demolition and removal of the electricity and heat generating station must be submitted to the relevant planning authority for approval.
Subject to obtaining the necessary consents and approvals, the decommissioning, demolition and removal of the electricity and heat generating station must be implemented in accordance with the plan approved under paragraph (1).
On the first anniversary of the operational site ceasing to be used for waste management purposes, the undertaker must notify the relevant planning authority of the same.
Annotations
Commencement
- I1
Sch. 2 para. 21 in force at 18.3.2017, see art. 1