Paragraph 4 Stages of authorised developmentI1
England, Wales and Scotland
(1)
No authorised development is to commence until a written scheme setting out all the stages of the authorised development has been submitted to and approved by the relevant planning authority, such scheme to include the following details—
(a)
confirmation whether the authorised development is to be carried out in a single stage or multiple stages;
(b)
if multiple stages, the chronological order of such stages; and
(c)
the date of commencement of each stage.
(2)
The authorised development must be carried out in accordance with the approved scheme.
Annotations
Commencement
- I1
Sch. 2 para. 4 in force at 19.8.2016, see art. 1