Paragraph 14 ContaminationI1

England and Wales

(1)

If, during the construction of the authorised development, contaminated land not previously identified in the environmental statement is found within the Order limits then no further works or actions relating to the authorised development are to be engaged or carried out (unless otherwise approved by the relevant planning authority) until an investigation and remediation scheme has been submitted to and approved by the relevant planning authority; and the scheme must include details of—

(a)

how the contaminated land is to be identified and assessed;

(b)

where remediation is required by the scheme, the remediation measures;

(c)

timescales for carrying out the remediation measures; and

(d)

any ongoing monitoring or mitigation requirements.

(2)

Where remediation measures are required by the investigation and remediation scheme then the remediation measures must be carried out no later than the times stipulated in the investigation and remediation scheme and in accordance with the investigation and remediation scheme.

(3)

In this requirement, expressions used both in this requirement and section 78A (preliminary) of the Environmental Protection Act 1990f1 have the same meaning as in that section.

Annotations

Commencement

I1

Sch. 2 para. 14 in force at 2.2.2015, see art. 1

Footnotes

f1

1990 c. 43. Section 78A was inserted by section 57 of the Environment Act 1995 (c. 25) and subsequently amended by section 86(1) and (2) of the Water Act 2003 (c. 37) and S.I. 2013/755.