Paragraph 7 Detailed offshore design parameters
(1)
The maximum number of gravity base structure foundations must not exceed 50 per cent of the total number of wind turbine generators, offshore electrical installations, accommodation platform and offshore artificial nesting structures combined.
(2)
No wind turbine generator, offshore transformer substation or offshore accommodation platform forming part of the authorised project is to be erected within the area hatched black and marked “offshore restricted build area” on the works plans, whose coordinates are specified below and shown on the offshore order limits and grid coordinates plan—
| Point | Latitude | Longitude |
|---|---|---|
| 150 | 53° 34′ 31.492″ N | 001° 04′ 32.616″ E |
| 151 | 53° 36′ 34.077″ N | 001° 08′ 26.916″ E |
| 152 | 53° 39′ 12.689″ N | 001° 28′ 43.588″ E |
| 845 | 53° 33′ 59.545″ N | 001° 03′ 36.079″ E |
| 846 | 53° 33′ 59.382″ N | 001° 03′ 35.074″ E |
| 847 | 53° 34′ 09.033″ N | 001° 03′ 52.365″ E |
| 848 | 53° 34′ 31.223″ N | 001° 04′ 32.133″ E |
| 849 | 53° 36′ 37.559″ N | 001° 19′ 54.519″ E |
| 850 | 53° 38′ 07.792″ N | 001° 29′ 20.432″ E |
| 851 | 53° 34′ 27.499″ N | 001° 06′ 28.034″ E |