OpenLegislation

Paragraph 78 Arbitration

Original text. Later amendments are not shown.

Save for differences or disputes arising under paragraph 7(2), 7(4) 8(1) and 9 any difference or dispute arising between the undertaker and National Grid Electricity Transmission Plc under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid Electricity Transmission Plc, be determined by arbitration in accordance with article 38 (arbitration).