Paragraph 16 Guillemot CIMP
Where the undertaker elects to submit a Guillemot CIMP under paragraph 2(1)(b) no offshore works are to commence until a plan for the work of the GCSG has been submitted to and approved by the Secretary of State. Such plan to include—
(a)
terms of Reference of the GCSG;
(b)
details of the membership of the GCSG which must include the relevant statutory nature conservation body and, where appropriate, the MMO and/or the relevant planning authority as core members;
(c)
details of the proposed schedule of meetings, timetable for preparation of the Guillemot CIMP and reporting and review periods; and
(d)
the dispute resolution mechanism.