Paragraph 12 Construction hoursI1
England, Wales and Scotland
Subject to sub-paragraphs (2) and (4), construction and demolition works must not take place except between—
7 a.m. and 7 p.m. on weekdays (excluding public holidays); and
7 a.m. and 4 p.m. on Saturdays (excluding public holidays),
unless otherwise agreed by the relevant planning authority.
Subject to sub-paragraph (4), the following works are permitted outside the hours referred to in sub-paragraph (1)—
emergency works; and
works which do not cause noise that is audible at the boundary of the Order limits.
Any emergency works carried out under sub-paragraph (2)(a) must be notified to the relevant planning authority within 72 hours of their commencement.
No piling operations may take place after 6 p.m., unless otherwise agreed by the relevant planning authority.
For the purpose of this Requirement, “construction works”—
does not include—
the arrival or departure of personnel on the site;
on-site briefings or meetings;
the use of welfare facilities;
non-intrusive activities, such as electrical installation and internal fit-out works;
archaeological investigations;
landscaping works; but
includes start up, shut down and deliveries.