Paragraph 18 Restoration of land used temporarily for constructionI1

England, Wales and Scotland

Any land within the Order limits that is used temporarily for construction must be reinstated to its former condition, or such condition as the relevant planning authority may approve, within 6 months of the completion of the authorised development.

Annotations

Commencement

I1

Sch. 2 para. 18 in force at 12.2.2016, see art. 1