Paragraph 3 Commissioning of authorised development: notice of commencement and completionI1
England, Wales and Scotland
(1)
Notice of the commencement of commissioning must be given to the relevant planning authority within 7 days of the date on which commissioning is commenced.
(2)
Notice of the completion of commissioning must be given to the relevant planning authority within 7 days of the date on which commissioning is completed.
(3)
In this Requirement, “commissioning” means the process of ensuring that all systems and components of the authorised development are installed, tested, and operable in accordance with the design and operational requirements of the undertaker.
Annotations
Commencement
- I1
Sch. 2 para. 3 in force at 12.2.2016, see art. 1