The authorised development must be carried out in accordance with the following plans and documents—
the conceptual surface water drainage system;
the environmental statement;
the existing site layout plan;
the design and access statement;
the land plan and site location plan;
the maximum parameters of works;
the site layout and works plan.
In this Requirement—
-
“conceptual surface water drainage system” means the document certified by the Secretary of State as the conceptual surface water drainage system under article 13;
-
“design and access statement” means the document certified by the Secretary of State as the design and access statement under article 13;
-
“existing site layout plan” means the plan certified by the Secretary of State as the existing site layout plan under article 13;
-
“maximum parameters of works” means the document certified by the Secretary of State as the maximum parameters of works under article 13.
Annotations
Commencement
- I1
Sch. 2 para. 4 in force at 12.2.2016, see art. 1