The Petroleum Act 1998 (Specified Pipelines) Order 2011
S.I. 2011/423 · Made 9 February 2011 · Extends to United Kingdom
Pipe-lines
Made 9th February 2011
Laid before Parliament 17th February 2011
Coming into force 6th April 2011
The Secretary of State makes this Order in exercise of the powers conferred by sections 24(2A) and 25(7)(b) of the Petroleum Act 1998f1.
Annotations to the whole text
Footnotes
- f1
-
1998 c. 17. Subsection (2A) was inserted into section 24 by paragraph 7(2) of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23).
Contents
- 1Citation and commencement
- 2Specified pipelines
- 3Transitional provisions: existing pipelines
- 4Transitional provisions: pending applications
- Signature
- Explanatory note
1Citation and commencementI1
This Order—
may be cited as the Petroleum Act 1998 (Specified Pipelines) Order 2011, and
comes into force on 6th April 2011.
2Specified pipelinesI1
Paragraph (2) specifies a description of pipelines for the purposes of section 24(2A) of the Petroleum Act 1998 (pipelines disregarded for the purposes of Part 3 of that Act etc).
The pipelines are any pipelines other than—
controlled pipelines used in relation to the exploration for, or exploitation of, petroleum;
controlled pipelines used in relation to unloading or storage offshore of relevant substances; F1...
controlled pipelines (except those described under sub-paragraph (b) or (c)) used in relation to the conveyance of hydrogen.
3Transitional provisions: existing pipelinesI1
Nothing in this Order applies in relation to a pipeline in respect of which, immediately before the date of coming into force of this Order, an authorisation under Part 3 of the Petroleum Act 1998 was in force.
4Transitional provisions: pending applicationsI1
Paragraph (2) applies where—
an application is made before the date of coming into force of this Order for an authorisation in respect of a pipeline under Part 3 of that Act; and
that application was not determined or withdrawn by that date.
An application described in paragraph (1)—
is not affected by this Order; and
if the application is granted, is an authorisation made under Part 3 of the Petroleum Act 1998.
Signature
Richard Benyon
Parliamentary Under Secretary of State
Department for Environment, Food and Rural Affairs
9th February 2011
Explanatory note
(This note is not part of the Order)
This Order specifies descriptions of pipelines which are to be disregarded for the purposes of Part 3 of the Petroleum Act 1998 (other than for the purposes of section 24(2A), under which this Order is made). Part 3 of that Act deals with submarine pipelines: see section 26 of that Act for the meaning of “pipeline”.
A full impact assessment of the effect that this Order will have on the costs of business, the voluntary sector and the public sector has been prepared. Copies are available from the Licensing Policy Team, Department for Environment, Food and Rural Affairs, Nobel House, 17 Smith Square, London SW1P 3JR and from Defra’s website at www.defra.gov.uk.