Planning and Infrastructure Act 2025 in Scotland
2025 c. 34 · Enacted 18 December 2025 · Extends to United Kingdom
An Act to make provision about infrastructure; to make provision about town and country planning; to make provision for a scheme, administered by Natural England, for a nature restoration levy payable by developers; to make provision about development corporations; to make provision about the compulsory purchase of land; to make provision about environmental outcomes reports; and for connected purposes.
[18th December 2025]
Be it enacted by the King’s most Excellent Majesty, by and with the advice and consent of the Lords Spiritual and Temporal, and Commons, in this present Parliament assembled, and by the authority of the same, as follows:—
Contents
- Part 1: Infrastructure
- Chapter 2: Electricity infrastructure
- Connections to the electricity transmission and distribution systems
- 14Connections to electricity network: licence and other modifications
- 15Scope of modification power under section 14
- 16Procedure relating to modifications under section 14
- 17Directions to modify connection agreements
- Consents for electricity infrastructure in Scotland
- 19Consents for generating stations and overhead lines: applications
- 21Proceedings for questioning certain decisions on consents
- 25Environmental impact assessments for electricity works
- Wind generating stations and seismic array systems
- 30Wind generating stations that may affect seismic array systems
- Chapter 3: Transport infrastructure
- Amendments to the Transport and Works Act 1992
- 46Extension to Scotland of certain amendments
- 47Power to make consequential amendments
- Part 6: Miscellaneous and general provision
- 116The Crown
- 117Extent
- 118Commencement and transitional provision
- 119Short title
- 2Paragraph 2
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 16Paragraph 16
- 18Paragraph 18
- 42Paragraph 42
- 43Paragraph 43
- 48Paragraph 48
- 49Paragraph 49
- 50Paragraph 50
- 51Paragraph 51
- 52Paragraph 52
14Connections to electricity network: licence and other modificationsI1 E+W+S
A relevant authority may modify—
the conditions of a particular electricity licence;
the terms of a particular electricity licence;
the standard conditions of electricity licences of a particular type;
a document maintained in accordance with the conditions of an electricity licence;
an agreement entered into in pursuance of a document maintained as mentioned in paragraph (d);
a qualifying distribution agreement.
A relevant authority may exercise the power under subsection (1) only for the purpose of improving the process for managing connections to the transmission system or the distribution system (and such an improvement may include changing the order in which connections are made).
The Secretary of State may direct the GEMA to exercise the power under subsection (1).
The Secretary of State may exercise the power under subsection (3) only for the purpose mentioned in subsection (2).
The power conferred by subsection (1) may not be exercised after the end of the period of three years beginning with the day on which this section comes into force.
Section 3A of the Electricity Act 1989 (principal objective and general duties) applies in relation to the functions of the Secretary of State and the GEMA under this section and sections 15 to 17 as it applies in relation to functions of the Secretary of State or the GEMA under Part 1 of that Act.
A relevant authority may under subsection (1) modify an agreement mentioned in subsection (1)(e) or a qualifying distribution agreement even if the effect of the modification might amount to a repudiation of the agreement.
In this section and sections 15 to 17—
-
“distribution system” has the same meaning as in Part 1 of the Electricity Act 1989 (see the definition of “distribute” in section 4(4) of that Act);
-
“electricity distributor” has the same meaning as in Part 1 of that Act (see section 6(9) of that Act);
-
“electricity licence” means a licence for the purposes of section 4 of that Act;
-
“the GEMA” means the Gas and Electricity Markets Authority;
-
“qualifying distribution agreement” means—
- (a)
the terms subject to which a connection is made by an electricity distributor in pursuance of section 16(1) of the Electricity Act 1989, or
- (b)
a special connection agreement as defined by section 22(1) of that Act;
- (a)
-
“relevant authority” means the Secretary of State or the GEMA;
-
“transmission system” has the same meaning as in Part 1 of the Electricity Act 1989 (see section 4(4) of that Act).
15Scope of modification power under section 14I1 E+W+S
The power conferred by section 14(1) to “modify” includes power to amend, add to or remove (and, in particular, includes power to make a person a party to an agreement or to discharge a party from its obligations under an agreement); and references in section 14, this section and section 16 to modification are to be construed accordingly.
The power conferred by section 14(1)—
may be exercised generally, only in relation to specified cases, or subject to exceptions (including by making provision for a case to be excepted only so long as specified conditions are satisfied);
may be exercised differently for different purposes or areas;
includes power to make incidental, supplementary, consequential or transitional modifications.
Provision included in an electricity licence by virtue of section 14(1)(a) or (c)—
may include provision of a kind mentioned in section 7 of the Electricity Act 1989;
need not relate to the activities authorised by the licence.
The modification under section 14(1) of part of a standard condition of an electricity licence does not prevent any other part of the condition from continuing to be regarded as a standard condition for the purposes of Part 1 of the Electricity Act 1989.
If under section 14(1) a relevant authority modifies the standard conditions of an electricity licence of a particular type, the GEMA must make the same modifications of those standard conditions for the purposes of their incorporation in electricity licences of that type granted after that time.
Provision included in an electricity licence by virtue of section 14(1)(b) may in particular include provision about the circumstances in which the licence may be revoked or suspended.
Provision included in an agreement by virtue of section 14(1)(e) or (f) may in particular include provision—
requiring specified conditions to be met before the taking of particular steps under the agreement;
about the procedure for varying the agreement.
In section 33 of the Utilities Act 2000 (standard conditions of electricity licences), in subsection (1)—
omit the “or” at the end of paragraph (k), and
at the end insert
“, or
(m)under section 14 of the Planning and Infrastructure Act 2025.”
16Procedure relating to modifications under section 14I1 E+W+S
Before making a modification under section 14, a relevant authority must consult—
the holder of any electricity licence proposed to be modified,
the Independent System Operator and Planner,
the GEMA or the Secretary of State (depending on which relevant authority is proposing to make the modification), and
such other persons as the relevant authority considers appropriate.
Subsection (1) may be satisfied by consultation carried out before the passing of this Act (as well as by consultation carried out after that time).
A relevant authority must publish details of any modifications made by it under section 14 as soon as reasonably practicable after they are made.
A relevant authority may exclude from publication under subsection (3) any information the publication of which would be likely to prejudice the commercial interests of any person.
In this section, “the Independent System Operator and Planner” means the person for the time being designated under section 162(1) of the Energy Act 2023.
17Directions to modify connection agreementsI1 E+W+S
A relevant authority may—
direct the Independent System Operator and Planner (“the ISOP”) to modify an agreement entered into by the ISOP pursuant to a document maintained in accordance with the conditions of an electricity licence;
direct an electricity distributor to modify a qualifying distribution agreement entered into by the electricity distributor.
A relevant authority may exercise the power conferred by subsection (1) only for the purpose of improving the process for managing connections to the transmission system or the distribution system (and such an improvement may include changing the order in which connections are made).
A direction under subsection (1) must describe the kinds of modification to be made by the person to whom it is given.
A direction under subsection (1) may also require the person to whom it is given to modify an agreement by including in it provision—
requiring specified conditions to be met before the taking of particular steps under the agreement;
about the procedure for varying the agreement.
A direction under subsection (1) may be expressed as having effect generally, in relation to cases within a description specified in the direction, or in relation to a particular case.
Before giving a direction under subsection (1), the relevant authority must consult—
the person to whom it proposes to give the direction, and
such other persons as the relevant authority considers appropriate.
Subsection (6) may be satisfied by consultation carried out before the passing of this Act (as well as by consultation carried out after that time).
A relevant authority must publish details of any direction it gives under subsection (1) as soon as reasonably practicable after the direction is given.
A relevant authority may exclude from publication under subsection (8) any information the publication of which would be likely to prejudice the commercial interests of any person.
A person to whom a direction is given under subsection (1) must comply with it, even if the effect of a modification made to an agreement as a result of the direction might amount to a repudiation of the agreement.
The power to give a direction under subsection (1) may not be exercised after the end of the period of three years beginning with the day on which this section comes into force.
A direction under subsection (1) may be varied or revoked by a subsequent direction given by a relevant authority.
In this section—
-
“the Independent System Operator and Planner” means the person for the time being designated under section 162(1) of the Energy Act 2023;
-
“modify” includes amend, add to and remove (and, in particular, includes making a person a party to an agreement and discharging a party from its obligations under an agreement).
In Schedule 6A to the Electricity Act 1989 (provisions imposing obligations enforceable as relevant requirements)—
in paragraph 4A (electricity system operator), after sub-paragraph (c) insert—
“(d)section 17(10) of the Planning and Infrastructure Act 2025 (duty to comply with direction under section 17 of that Act).”;
in paragraph 5 (distribution licence holders), after sub-paragraph (g) insert—
“(h)section 17(10) of the Planning and Infrastructure Act 2025 (duty to comply with direction under section 17 of that Act).”
19Consents for generating stations and overhead lines: applicationsI1I2I3I4 E+W+S
Schedule 8 to the Electricity Act 1989 (consents of the Secretary of State and the Scottish Ministers under sections 36 and 37) is amended as follows.
After paragraph 1 insert—
“Applications made to the Scottish Ministers for consent
1A(1)The Secretary of State or the Scottish Ministers may by regulations make provision about the following matters in relation to applications to the Scottish Ministers for consent under section 36 or 37.
(2)The matters are—
(a)the steps a person must take before making an application;
(b)the information that must be included in an application;
(c)an acceptance stage, during which the Scottish Ministers must assess an applicant’s compliance with any requirements imposed by the regulations in order to decide whether or not to accept the application;
(d)fees to be paid to the Scottish Ministers—
(i)on application, or
(ii)for anything done by them in relation to a proposed application;
(e)requests by the Scottish Ministers for additional information to aid their decision whether or not to accept an application or to grant consent.
(3)The steps that may be the subject of provision made by virtue of sub-paragraph (2)(a) include—
(a)notifying prescribed persons of the proposed application,
(b)publicising the proposed application, and
(c)carrying out a consultation about the proposed application.”
In paragraph 2 (objections by relevant planning authority)—
in sub-paragraph (1), for “Secretary of State for his” substitute “appropriate authority for a”;
in sub-paragraph (2), at the beginning insert “In the case of an application made to the Secretary of State,”;
after sub-paragraph (2) insert—
“(2A)In the case of an application made to the Scottish Ministers, where the relevant planning authority notify the Scottish Ministers that they object to the application and their objection is not withdrawn, the Scottish Ministers—
(a)must appoint a person (referred to in this Schedule as the “reporter”) to examine the application, and
(b)before determining whether to give their consent, must consider the objection and the reporter’s final report.
See paragraph 2A for the process that must be followed by the reporter.”;
in sub-paragraph (4)—
after “(2)” insert “or (2A)”;
for “Secretary of State” substitute “appropriate authority”;
in sub-paragraph (5), for “Secretary of State” substitute “appropriate authority”.
After paragraph 2 insert—
“Procedure following objection by relevant planning authority: Scotland
2A(1)A reporter appointed under paragraph 2(2A)(a) must make proposals as regards the appropriate procedure for examining the application.
(2)The appropriate procedure may consist of one or more of the following—
(a)considering—
(i)the objection by the relevant planning authority,
(ii)any other objections made in accordance with regulations under paragraph 3(1)(c), and
(iii)any other representations made in accordance with an enactment;
(b)considering new written representations about the application from persons specified by the reporter;
(c)holding one or more hearing sessions;
(d)carrying out an inspection of the land to which the application relates;
(e)holding a public inquiry.
(3)Where the reporter proposes a procedure that includes proceedings within sub-paragraph (2)(b), (c) or (e), the proposal must include a statement of the issues that are proposed to be within the scope of each of those proceedings.
(4)The reporter must—
(a)publish the proposals,
(b)notify all interested parties of the proposals, and
(c)invite written representations about the proposals before the end of the time period specified by the reporter.
(5)The published proposals must include or be accompanied by an explanation of the reasons for the proposals.
(6)The reporter may hold a meeting to hear representations about the proposals.
(7)After considering the representations, the reporter must—
(a)decide on the appropriate procedure for examining the application, and
(b)publish that decision.
(8)The published decision must include or be accompanied by an explanation of—
(a)the reasons for the decision,
(b)the intended time period for the carrying out of the procedure, and
(c)the intended time period within which the reporter will send a final report to the Scottish Ministers.
(9)Sub-paragraph (3) applies to the reporter’s decision as it applies to the reporter’s proposals.
(10)On completing the examination, the reporter must prepare and send to the Scottish Ministers a final report setting out the reporter’s recommendations on the application.
(11)In this paragraph, “interested party” means—
(a)the applicant,
(b)the relevant planning authority which made the objection under paragraph 2(2A),
(c)any person who has made an objection in accordance with regulations under paragraph 3, or
(d)any person who has made representations in accordance with any other enactment.
(12)The Secretary of State or the Scottish Ministers may by regulations make provision amending or setting out further detail about the procedure set out in this paragraph. (See also paragraph 7B(2)(e).)
(13)A statutory instrument containing regulations under this paragraph is not to be made by the Secretary of State unless a draft of the instrument has been laid before, and approved by a resolution of, each House of Parliament.
(14)Regulations made by the Scottish Ministers under this paragraph are subject to the affirmative procedure.”
After paragraph 7A insert—
“Applications to the Scottish Ministers: time limits
7B(1)The Secretary of State or the Scottish Ministers may by regulations specify a time limit for actions that may or must be taken in relation to an application to the Scottish Ministers for consent under section 36 or 37.
(2)The regulations may, for example, specify a time limit for—
(a)a person to comply with a requirement of regulations under paragraph 1A;
(b)a person to respond to a pre-application consultation (see paragraph 1A(3)(c));
(c)a person who is notified of an application in accordance with an enactment to provide their opinion or advice on the application;
(d)a relevant planning authority to object to an application under paragraph 2(2A);
(e)a reporter to take any steps required by paragraph 2A;
(f)the Scottish Ministers to decide an application.
(3)The regulations may include provision about the consequences of failure to comply with a time limit.
(4)Where regulations under this paragraph specify a time limit for the completion of an acceptance stage (see paragraph 1A(2)(c)), the regulations may not permit the extension of that limit.”
The amendments made by subsection (3) do not affect the continued application in relation to the Scottish Ministers of regulations made under paragraph 2(3) of Schedule 8 to the Electricity Act 1989 before this section comes into force.
21Proceedings for questioning certain decisions on consentsI1 E+W+S
For subsection (3) substitute—
“(3)This section applies to a decision under any of the following—
(a)section 36 (application for consent for generating station);
(b)section 36C (application for variation of section 36 consent);
(c)section 37 (application for consent for overhead lines);
(d)section 37A (application for variation of section 37 consent);
(e)section 37B (variation of consents by Scottish Ministers);
(f)section 37C (consents and variation of consents in Scotland: correction of errors).”
In subsection (4), for “taken” substitute “published by the Scottish Ministers”.
In the heading, for “under section 36” substitute “of the Scottish Ministers”.
In Schedule 8 to the Electricity Act 1989, in paragraph 5B (proceedings for questioning certain decisions under paragraph 3(2)), in sub-paragraph (4), for “taken” substitute “published by the Scottish Ministers”.
In section 237 of the Town and Country Planning (Scotland) Act 1997 (challenges to validity of development plans and certain orders, decisions and directions), in subsection (3), after paragraph (b) insert—
“(ba)any decision to give a direction under section 57(2) or (2ZA);”.
The amendments made by this section apply only in relation to decisions made on or after the date on which this section comes into force.
25Environmental impact assessments for electricity worksI1 S
The Secretary of State or the Scottish Ministers may by regulations amend the Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2017 (S.S.I. 2017/101) (the “2017 Regulations”) by making provision described in subsection (2) in connection with environmental impact assessments and applications made to the Scottish Ministers for—
consent granted under section 36 or 37 of the Electricity Act 1989 (consent for construction etc of generating stations or for overhead lines), or
variation of consent granted under section 36 of that Act.
That provision is—
provision for the Scottish Ministers to refuse an application in respect of Schedule 2 development that is not accompanied by an EIA report if the development has not been the subject of a screening opinion;
provision for the Scottish Ministers to charge developers fees for screening opinions and scoping opinions;
provision about the sending of copies of EIA reports to the Scottish Ministers;
provision about the publication by developers of the information listed in regulation 14(2) of the 2017 Regulations (information about EIA reports);
provision about making EIA reports available for inspection;
provision about time limits for the consultation bodies and other public bodies to make representations to the Scottish Ministers about scoping opinions and EIA reports;
provision about time limits for the consultation bodies and other public bodies to enter into consultation with developers about, and to make available, information relevant to the preparation of EIA reports;
provision about time limits for developers to provide additional information to the Scottish Ministers;
provision about the publication by developers of the information listed in regulation 20(3) of the 2017 Regulations (information about additional information);
provision about making additional information available for inspection;
provision about the publication by developers of the information listed in regulation 23(2) of the 2017 Regulations (information about decisions);
provision that the Secretary of State or the Scottish Ministers consider appropriate for securing that the procedures under the 2017 Regulations operate effectively, or more effectively, alongside the procedures under regulations made under section 36C of the Electricity Act 1989 or paragraph 1A or 7B of Schedule 8 to that Act (inserted by section 19 of this Act).
The Secretary of State or the Scottish Ministers may by regulations amend the 2017 Regulations by making provision described in subsection (4) in connection with environmental impact assessments and applications made to the Scottish Ministers for variation of consent granted under section 37 of the Electricity Act 1989.
That provision is—
provision requiring an environmental impact assessment in respect of the proposed variation to be carried out before Scottish Ministers—
vary the consent, or
direct that planning permission is deemed to be granted under section 57(2) or (2ZA) of the Town and Country Planning (Scotland) Act 1997 in respect of EIA development;
provision requiring the Scottish Ministers to take the environmental information into account when carrying out an environmental impact assessment in respect of the proposed variation;
provision applying provisions of the 2017 Regulations (including provisions amended by regulations under subsection (1)), with or without modifications;
provision that the Secretary of State or the Scottish Ministers consider appropriate for securing that the procedures under the 2017 Regulations operate effectively, or more effectively, alongside the procedures under regulations made under section 37A of the Electricity Act 1989 (inserted by section 20 of this Act).
Regulations under this section may—
make different provision for different purposes or different areas;
make consequential or supplementary provision;
make transitional provision.
Regulations under this section made by the Secretary of State are to be made by statutory instrument.
A statutory instrument containing regulations made by the Secretary of State under this section is subject to annulment in pursuance of a resolution of either House of Parliament.
Before making regulations under this section, the Secretary of State must consult the Scottish Ministers.
For regulations under this section made by the Scottish Ministers, see section 27 of the Interpretation and Legislative Reform (Scotland) Act 2010 (asp 10) (Scottish statutory instruments).
Regulations made by the Scottish Ministers under this section are subject to the negative procedure (see section 28 of the Interpretation and Legislative Reform (Scotland) Act 2010 (asp 10)).
Before making regulations under this section, the Scottish Ministers must consult the Secretary of State.
In this section, subject to subsection (13), the following terms have the same meaning as they have in the 2017 Regulations—
-
“additional information”
-
“the consultation bodies”
-
“developer”
-
“EIA development”
-
“EIA report”
-
“environmental impact assessment”
-
“environmental information”
-
“Schedule 2 development”
-
“scoping opinion”
-
“screening opinion”.
In subsections (3) and (4), those terms have the same meaning in connection with applications for variation of consent granted under section 37 of the Electricity Act 1989 as they have, in the 2017 Regulations, in connection with applications for variation of consent granted under section 36 of that Act.
30Wind generating stations that may affect seismic array systemsI1 E+W+S
The Secretary of State may make regulations about planning permissions or consents relating to wind generating stations that may affect the functioning of a relevant seismic array system.
A “relevant seismic array system” is a spatially distributed system of linked seismometers, arranged so as to enhance the detection and characterisation of seismic signals, that—
is used for defence purposes, and
is in use on the day on which this Act is passed.
The regulations may provide for—
an exclusion zone, and
a restricted zone,
around a relevant seismic array system.
The regulations may—
require a planning decision-maker to refuse, or decline to determine or accept, a planning application relating to a wind generating station that is (or would be) situated in an exclusion zone;
provide that a relevant development order or MCA scheme may not be made if it would grant planning permission for development relating to a wind generating station that is (or would be) situated in an exclusion zone;
allow the Secretary of State to direct that a relevant development order or MCA scheme may not be made if it would grant such planning permission.
The regulations may, in relation to a planning application relating to a wind generating station that is (or would be) situated in a restricted zone—
require the applicant to provide specified information about the seismic impact of the proposals (“seismic impact information”) to which their application relates;
require the planning decision-maker to use the seismic impact information in a specified way when determining the application (including when determining conditions relating to a permission or consent);
require the planning decision-maker to refuse, or decline to determine or accept, the application in specified circumstances;
require the planning decision-maker to provide the Secretary of State with the seismic impact information, and to seek the Secretary of State’s views on the seismic impact of the proposals;
require the planning decision-maker to refuse, or decline to determine or accept, the application if the Secretary of State objects to it on grounds relating to the seismic impact of the proposals.
The regulations may—
require a person proposing to make a relevant development order or MCA scheme to consult the Secretary of State if the order or scheme would grant planning permission for development relating to a wind generating station that is (or would be) situated in a restricted zone;
allow the Secretary of State to direct that a relevant development order or MCA scheme may not be made if it would grant such planning permission.
The regulations may include provision about the procedure for planning applications to which they relate, such as—
provision enabling or requiring a planning decision-maker to decline to determine or accept an application;
provision modifying the process for determining an application;
provision allowing the Secretary of State to give a direction to the planning-decision maker about the procedure for an application;
provision modifying or disapplying a right of appeal or review;
provision disapplying a duty imposed on a planning decision-maker when determining an application.
The regulations may require a planning decision-maker to have regard to guidance issued by the Secretary of State.
Regulations under this section may—
amend or repeal provision contained in an Act of Parliament or an Act of the Scottish Parliament;
make different provision for different purposes or areas;
make provision binding the Crown;
make transitional, transitory or saving provision;
make incidental, supplementary or consequential provision.
Regulations under this section are to be made by statutory instrument.
A statutory instrument containing regulations under this section which amend or repeal provision contained in an Act of Parliament or an Act of the Scottish Parliament may not be made unless a draft of the instrument has been laid before, and approved by a resolution of, each House of Parliament.
Any other statutory instrument containing regulations under this section is subject to annulment in pursuance of a resolution of either House of Parliament.
If a draft of a statutory instrument containing regulations under this section would, apart from this subsection, be treated for the purposes of the standing orders of either House of Parliament as a hybrid instrument, it is to proceed in that House as if it were not such an instrument.
In this section—
-
“MCA scheme” means a masterplan consent area scheme made under Part 3 of the Town and Country Planning (Scotland) Act 1997;
-
“planning application” means—
- (a)
an application for planning permission under Part 3 or Part 13 of the Town and Country Planning Act 1990,
- (b)
an application for planning permission under Part 3 or Part 12 of the Town and Country Planning (Scotland) Act 1997,
- (c)
an application for an order granting development consent under section 37 of the Planning Act 2008, or
- (d)
an application under section 36 or 36C of the Electricity Act 1989 (consent for construction etc of generating station);
- (a)
-
“planning decision-maker” means a person who determines a planning application;
-
“relevant development order” means—
- (a)
a local development order made under section 61A of the Town and Country Planning Act 1990;
- (b)
a Mayoral development order made under section 61DA of that Act;
- (c)
a neighbourhood development order made under section 61E of that Act;
- (d)
a development order made under section 30 of the Town and Country Planning (Scotland) Act 1997;
- (a)
-
“wind generating station” means a generating station that generates electricity from wind.
46Extension to Scotland of certain amendmentsI1 S
The amendments made to the Transport and Works Act 1992 by the following provisions are extended to Scotland—
Schedule 3 to the Environmental Impact Assessment (Miscellaneous Amendments Relating to Harbours, Highways and Transport) Regulations 2017 (S.I. 2017/1070);
regulation 4(3) and (4) of the Merchant Shipping and Other Transport (Environmental Protection) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/311).
47Power to make consequential amendmentsI1 E+W+S
Regulations under this section may amend—
an Act, or
an Act or Measure of Senedd Cymru,
passed before the end of the session of Parliament in which this Act is passed.
Regulations under this section may include incidental, supplemental, transitional and saving provision.
A statutory instrument containing (whether alone or with other provision) regulations made in reliance on subsection (2) may not be made unless a draft of the statutory instrument containing them has been laid before, and approved by a resolution of, each House of Parliament.
Any other statutory instrument containing regulations under this section is subject to annulment in pursuance of a resolution of either House of Parliament.
116The CrownI1
The amendments made by this Act bind the Crown to the extent that the provisions amended bind the Crown.
117ExtentI1
Subject to subsection (2), an amendment, repeal or revocation made by this Act has the same extent as the provision amended, repealed or revoked.
Paragraphs 40 and 44 of Schedule 5 extend to England and Wales only.
118Commencement and transitional provisionI1
In Part 1—
sections 1 and 2 come into force on such day as the Secretary of State may by regulations appoint;
section 3 comes into force on the day on which this Act is passed;
sections 4 to 9 come into force on such day as the Secretary of State may by regulations appoint;
section 10 comes into force at the end of the period of two months beginning with the day on which this Act is passed;
in section 19—
section 20 comes into force at the end of the period of two months beginning with the day on which this Act is passed, except that it comes into force on the day on which this Act is passed so far as it confers power to make regulations;
section 21 comes into force at the end of the period of two months beginning with the day on which this Act is passed;
section 25 comes into force on the day on which this Act is passed;
section 26 comes into force at the end of the period of two months beginning with the day on which this Act is passed;
section 27 comes into force on the day on which this Act is passed;
section 28 comes into force at the end of the period of two months beginning with the day on which this Act is passed;
section 29 comes into force at the end of the period of two months beginning with the day on which this Act is passed, except that it comes into force on the day on which this Act is passed so far as it confers power to make regulations;
section 30 comes into force at the end of the period of two months beginning with the day on which this Act is passed;
section 33 comes into force on such day as the Secretary of State may by regulations appoint;
section 36 comes into force on such day as the Secretary of State may by regulations appoint;
in section 40—
subsections (1) and (2) come into force at the end of the period of two months beginning with the day on which this Act is passed;
subsection (3) comes into force on such day as the Secretary of State may by regulations appoint;
section 43 comes into force on such day as the Secretary of State may by regulations appoint;
section 46 comes into force on the day on which this Act is passed;
section 47 comes into force at the end of the period of two months beginning with the day on which this Act is passed;
section 48(2) and (3) come into force—
in relation to applications made to the Secretary of State, on the day on which the first relevant regulations made by the Secretary of State come into force;
in relation to applications made to the Scottish Ministers, on the day on which the first relevant regulations made by the Scottish Ministers come into force;
in relation to applications made to the Welsh Ministers, on the day on which the first relevant regulations made by the Welsh Ministers come into force;
and in this paragraph “relevant regulations” means regulations under paragraph 9A of Schedule 3 to the Harbours Act 1964 (inserted by section 48(4));
In Part 2—
section 51 comes into force on such day as the Secretary of State may by regulations appoint, except that it comes into force on the day on which this Act is passed so far as it confers power to make regulations;
section 56 comes into force at the end of the period of two months beginning with the day on which this Act is passed;
section 57 comes into force on such day as the Secretary of State may by regulations appoint;
section 58(4) to (8) come into force at the end of the period of two months beginning with the day on which this Act is passed.
Part 4 comes into force on such day as the Secretary of State may by regulations appoint.
In Part 5—
section 105 comes into force at the end of the period of two months beginning with the day on which this Act is passed;
section 106 comes into force on such day as the Secretary of State may by regulations appoint;
section 107 comes into force at the end of the period of two months beginning with the day on which this Act is passed;
sections 108 and 109 come into force on such day as the Secretary of State may by regulations appoint;
section 112 comes into force at the same time as section 18 of the Neighbourhood Planning Act 2017;
section 114 comes into force at the end of the period of two months beginning with the day on which this Act is passed.
The Secretary of State may by regulations make transitional, transitory or saving provision in connection with the coming into force of any provision of this Act.
Regulations under this section—
are to be made by statutory instrument;
may make different provision for different purposes or different areas.
119Short titleI1
This Act may be cited as the Planning and Infrastructure Act 2025.
2I1I2
Schedule 3 to ALA 1981 applies to the acquisition of new rights under section 89, with the following modification.
Paragraph 4(2) of that Schedule (orders to be subject to special parliamentary procedure in certain cases involving local authority or statutory undertakers’ land) does not apply to the acquisition of an interest in land by Natural England acting under section 89.
4I1I2
Natural England may give a direction before the completion of the acquisition that paragraph 3(2) is not to apply to any right or apparatus specified in the direction.
5I1I2
Paragraph 3(2) is subject to any agreement which may be made (whether before or after the completion of the acquisition) between—
Natural England, and
the person—
in whom the right or apparatus concerned is vested, or
to whom it belongs.
6I1I2
Paragraph 3(2) does not apply to—
any right vested in statutory undertakers for the purpose of carrying on their undertaking,
any apparatus belonging to statutory undertakers for that purpose,
any right conferred by, or in accordance with, the electronic communications code on the operator of an electronic communications code network, or
any electronic communications apparatus kept installed for the purposes of any such network.
In sub-paragraph (1) “statutory undertakers” means persons who are, or are deemed to be, statutory undertakers for the purposes of any provision of Part 11 of the Town and Country Planning Act 1990; and “undertaking” is to be read in accordance with section 262 of that Act (meaning of “statutory undertakers”).
7I1I2
Any person who suffers loss by the extinguishment of a right, or the vesting of any apparatus, under paragraph 3 is entitled to compensation from Natural England.
Any compensation payable under this paragraph is to be determined in accordance with the Land Compensation Act 1961.
9I1I2
Section 7 of CPA 1965 is to have effect as if for the words of that section there were substituted—
“Measure of compensation in case of acquisition of new right
7(1)In assessing the compensation to be paid by the acquiring authority under this Act regard shall be had not only to the extent (if any) to which the value of the land over which the right is acquired is depreciated by the acquisition but also to the damage (if any) to be sustained by the owner of the land by reason of injurious affection of other land of the owner by the exercise of the right.
(2)The modifications subject to which subsection (1) of section 44 of the Land Compensation Act 1973 (compensation for injurious affection) is to have effect, as applied by subsection (2) of that section to compensation for injurious affection under this section, are that—
(a)for “land is acquired or taken” there is substituted “a right over land is acquired”; and
(b)for “acquired or taken from him” there is substituted “over which the right is exercisable”.”
10I1I2
Section 8(1) of CPA 1965 is to have effect as if references to acquiring land were to acquiring a right in the land.
Schedule 2A to CPA 1965 is to be read as if, for the words of that Schedule, there were substituted—
“Schedule 2A
Counter-notice requiring purchase of land
Introduction
1(1)This Schedule applies where an acquiring authority serve a notice to treat in respect of a right over the whole or part of a house, building or factory.
(2)But see section 2A of the Acquisition of Land Act 1981 (under which a compulsory purchase order can exclude from this Schedule land that is 9 metres or more below the surface).
2In this Schedule “house” includes any park or garden belonging to a house.
Counter-notice requiring purchase of land
3A person who is able to sell the house, building or factory (“the owner”) may serve a counter-notice requiring the authority to purchase the owner’s interest in the house, building or factory.
4A counter-notice under paragraph 3 must be served within the period of 28 days beginning with the day on which the notice to treat was served.
Response to counter-notice
5On receiving a counter-notice the acquiring authority must decide whether to—
(a)withdraw the notice to treat,
(b)accept the counter-notice, or
(c)refer the counter-notice to the Upper Tribunal.
6The authority must serve notice of their decision on the owner within the period of 3 months beginning with the day on which the counter-notice is served (“the decision period”).
7If the authority decide to refer the counter-notice to the Upper Tribunal they must do so within the decision period.
8If the authority do not serve notice of a decision within the decision period they are to be treated as if they had served notice of a decision to withdraw the notice to treat at the end of that period.
9If the authority serve notice of a decision to accept the counter-notice, the compulsory purchase order and the notice to treat are to have effect as if they included the owner’s interest in the house, building or factory.
Determination by Upper Tribunal
10On a referral under paragraph 7 the Upper Tribunal must determine whether the acquisition of the right would—
(a)in the case of a house, building or factory, cause material detriment to the house, building or factory, or
(b)in the case of a park or garden, seriously affect the amenity or convenience of the house to which the park or garden belongs.
11In making its determination, the Upper Tribunal must take into account—
(a)the effect of the acquisition of the right,
(b)the proposed use of the right, and
(c)if the right is proposed to be acquired for works or other purposes extending to other land, the effect of the whole of the works and the use of the other land.
12If the Upper Tribunal determines that the acquisition of the right would have either of the consequences described in paragraph 10 it must determine how much of the house, building or factory the authority ought to be required to take.
13If the Upper Tribunal determines that the authority ought to be required to take some or all of the house, building or factory the compulsory purchase order and the notice to treat are to have effect as if they included the owner’s interest in that land.
14(1)If the Upper Tribunal determines that the authority ought to be required to take some or all of the house, building or factory, the authority may at any time within the period of 6 weeks beginning with the day on which the Upper Tribunal makes its determination withdraw the notice to treat in relation to that land.
(2)If the acquiring authority withdraws the notice to treat under this paragraph they must pay the person on whom the notice was served compensation for any loss or expense caused by the giving and withdrawal of the notice.
(3)Any dispute as to the compensation is to be determined by the Upper Tribunal.”
11I1I2
The provisions of CPA 1965 mentioned in sub-paragraph (2) (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land) are to be read as if they were modified in accordance with sub-paragraph (3).
The provisions are—
section 9(4) (failure of owners to convey),
paragraph 10(3) of Schedule 1 (owners under incapacity),
paragraph 2(3) of Schedule 2 (absent and untraced owners), and
paragraphs 2(3) and 7(2) of Schedule 4 (common land).
The provisions are to be read as if they were modified so as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be acquired compulsorily is vested absolutely in the acquiring authority.
12I1I2
Section 11 of CPA 1965 (powers of entry) is to be read as if it were modified so as to secure that, where the acquiring authority have served notice to treat in respect of any right as well as the notice required by subsection (1) of that section (as it applies to a compulsory acquisition under section 89), they have power, exercisable in the same circumstances and subject to the same conditions, to enter for the purpose of exercising that right; and sections 11A (powers of entry: further notices of entry), 11B (counter-notice requiring possession to be taken on specified date), 12 (penalty for unauthorised entry) and 13 (entry on enforcement officer’s or sheriff’s warrant in the event of obstruction) of that Act are modified accordingly.
13I1I2
Section 20 of CPA 65 (compensation for short-term tenants) is to be read as if it were modified so as to secure that persons with such interests as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory purchase of the interests but taking into account only the extent (if any) of such interference with such interests as is actually caused, or likely to be caused, by the exercise of the right concerned.
14I1I2
Section 22 of CPA 65 (protection of acquiring authority’s possession of land where by inadvertence an interest in the land has not been purchased) is to be read as if it were modified so as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right concerned, subject to compliance with that section as respects compensation.
16I1I2
The modifications of CP(VD)A 1981 referred to in paragraph 15(a) are as follows.
References to CPA 1965 are, in appropriate contexts, to be read (according to the requirements of the particular context) as referring to, or as including references to—
the right acquired or to be acquired, or
the land over which the right is, or is to be, exercisable.
References to CPA 1965 are to be read as references to that Act as it applies to the compulsory acquisition of a right under section 89.
Section 8(1) (vesting, and right to enter and take possession) is to be read as securing that—
a general vesting declaration in respect of any right vests the right in the acquiring authority on the vesting date, and
as from the vesting date, the acquiring authority has power, exercisable in the same circumstances and subject to the same conditions, to enter land for the purpose of exercising that right as if the circumstances mentioned in paragraph (a) and (b) of section 8(1) had arisen.
Section 9(2) (right of entry under section 8(1) not exercisable in respect of land subject to certain tenancies unless notice has been served on occupiers of the land) is to be read as requiring a notice served by the appropriate authority under that provision to refer to the authority’s intention to enter land specified in the notice in order to exercise the right.
In section 10(1) (acquiring authority’s liability on vesting of the land), the reference to the acquiring authority’s taking possession of the land under section 11 of CPA 1965 is to be read as a reference to the authority’s exercising the power to enter the land under that provision as modified by paragraph 12 of this Schedule.
Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration) is to be read as if—
in paragraph 1(1), for “part only of” there were substituted “only the acquisition of a right over”;
paragraph 1(2) were omitted;
references to the land proposed to be acquired were (subject to paragraph (e) below) to the right proposed to be acquired;
references to the additional land were to the house, building or factory over which the right is proposed to be exercisable;
in paragraphs 14 and 15, references to the severance of land proposed to be acquired were to the acquisition of the right; and
in paragraph 15, after “in addition to” there were inserted “or in substitution for”.
18I1I2
Section 5A (relevant valuation date) of the Land Compensation Act 1961 is to be read as if for subsections (5A) and (5B) there were substituted—
“(5A)If—
(a)the acquiring authority enters on land for the purpose of exercising a right in pursuance of a notice of entry under section 11(1) of the Compulsory Purchase Act 1965 (as modified by paragraph 12 of Schedule 4 to the Planning and Infrastructure Act 2025),
(b)the acquiring authority is subsequently required by a determination under paragraph 13 of Schedule 2A to the 1965 Act (as substituted by paragraph 10 of Schedule 4 to the Planning and Infrastructure Act 2025) to acquire an interest in the land, and
(c)the acquiring authority enters on and takes possession of that land,
the authority is deemed for the purposes of subsection (3)(a) to have entered on that land when it entered on that land for the purpose of exercising that right.
(5B)If—
(a)a right over land is the subject of a general vesting declaration,
(b)by virtue of paragraph 11(2) or 16(2) of Schedule A1 to the Compulsory Purchase (Vesting Declarations) Act 1981, the declaration has effect as if it included an interest in the land, and
(c)the vesting date for the right is different from the vesting date for the interest in the land,
the first of the vesting dates is deemed for the purposes of subsection (4)(a) to be the vesting date for the whole of the land.”
42I1I2
In section 74A (deemed discharge of planning conditions), in subsection (2A)—
after “to” insert
“—”;
(a)
at the end insert
“, or
(b)a condition that Natural England has requested under Part 3 of the Planning and Infrastructure Act 2025 (see sections 61(10) and 95 of that Act).”
43I1I2
In section 100ZA (restrictions on power to impose planning conditions in England), in subsection (6), after “apply” insert
“—
(a)in relation to a condition that Natural England has requested under Part 3 of the Planning and Infrastructure Act 2025 (see sections 61(10) and 95 of that Act), or”.
(b)
48I1I2
In regulation 9 (duties relating to compliance with the Directives)—
after paragraph (2) insert—
“(2A)Paragraph (1) does not apply to functions exercisable under or by virtue of Part 3 of the Planning and Infrastructure Act 2025 (development and nature recovery).”;
after paragraph (3) insert—
“(3A)Paragraph (3) does not apply to functions exercised by a competent authority in connection with an environmental delivery plan within the meaning of Part 3 of the Planning and Infrastructure Act 2025.”
49I1I2
In regulation 55 (licences for certain activities relating to animals or plants), after paragraph (10) insert—
“(10A)The maximum time period for a licence set out in paragraph (10) does not apply to—
(a)a licence granted to Natural England to facilitate the carrying out of any conservation measures within the meaning of Part 3 of the Planning and Infrastructure Act 2025, or
(b)a licence that, by virtue of paragraph 4 of Schedule 3 to the Planning and Infrastructure Act 2025, is treated as having been granted to a developer under regulation 55.”
50I1I2
In regulation 58 (relevant licensing body)—
in paragraph (2), at the beginning insert “Subject to paragraph (2A),”;
after paragraph (2) insert—
“(2A)In the case of a licence granted to Natural England under regulation 55(1) for a purpose specified in any of paragraph (2)(a) to (d) of that regulation, to facilitate the carrying out of any conservation measures, “relevant licensing body” means the Secretary of State.”;
in paragraph (3), at the beginning insert “Subject to paragraph (4A),”;
after paragraph (4) insert—
“(4A)In the case of a licence that, by virtue of paragraph 4 of Schedule 3 to the Planning and Infrastructure Act 2025, is treated as having been granted to a developer under regulation 55(1) for any of the purposes specified in regulation 55(2)(e) to (g), “relevant licensing body” means—
(a)so far as the licence relates to the restricted English inshore region, the Marine Management Organisation; and
(b)otherwise, Natural England.”;
in paragraph (6), for “paragraph (2)” substitute “this regulation”;
at the end insert—
“(7)In paragraph (2A), “conservation measure” has the same meaning as in Part 3 of the Planning and Infrastructure Act 2025 (development and nature recovery).”
51I1I2
In regulation 62 (application of the provisions of Chapter 1 of Part 6), after paragraph (1) insert—
“(1A)But the requirements of the assessment provisions and the review provisions do not apply in relation to an environmental delivery plan or any conservation measures under it.
(1B)In paragraph (1A), “environmental delivery plan” and “conservation measures” have the same meaning as in Part 3 of the Planning and Infrastructure Act 2025 (development and nature recovery).”
52I1I2
In regulation 63 (assessment of implications for European sites etc), in paragraph (7), at the end insert—
“See also paragraph 1 of Schedule 3 to the Planning and Infrastructure Act 2025 (environmental delivery plans: effect on environmental obligations).”