Paragraph 3 Cost-benefit analysisF1

An application to an enforcing authority under regulation 10 for a permit to operate a new installation, carrying out an activity with a total net thermal input exceeding 20 megawatts and generating electricity must be accompanied by a cost-benefit analysis that assesses the costs and benefits of operating the installation or converting the installation to operate as a high-efficiency cogeneration installation.