Article 3 Development consent etc. granted by the OrderI1
England and Wales
Subject to the other terms of this Order, including the Requirements and the provisions and conditions of the deemed Marine Licence, the undertaker is granted—
development consent for the authorised development to be carried out within the Order limits; and
consent to use the authorised development for the purpose for which it is designed including use of the cavities to be created for the underground storage of gas.
Paragraph (1) does not relieve the undertaker of any requirement to obtain any permit or licence under any legislation that may be required from time to time to authorise the use of the authorised development for any purpose other than the matters referred to in section 33(1) of the 2008 Act.
Annotations
Commencement
- I1
Art. 3 in force at 7.8.2015, see art. 1